648 W AMADOR ST 90012

Certificate Information: 648 W AMADOR ST 90012

Application / Permit
20016-10000-28980
Plan Check / Job No.
B20LA20876
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO EXISTING SINGLE FAMILY DWELLING INCLUDING ASSOCIATED STRUCTURAL UPGRADES,ATTIC CONVERSION AND INCREASING THE PITCH ON PORTION OF THE ROOF.
Permit Issued
Issued on 5/30/2023
Issuing Office
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 ARMEN JIVALAGIAN
Corrections Issued 12/24/2020 ARMEN JIVALAGIAN
Quality Review Completed 12/29/2020 PETER KIM
Building Plans Picked Up 1/6/2021 APPLICANT
Applicant returned to address corrections 2/10/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 2/24/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 5/5/2021 ARMEN JIVALAGIAN
Plan Check Approved 12/15/2022 ARMEN JIVALAGIAN
Issued 5/30/2023 APPLICANT
CofO in Progress 4/3/2026 RONNIE MEDINA
Permit Finaled 4/7/2026 DEROLD HAUFF
CofO Issued 4/7/2026 DEROLD HAUFF
Permit Finaled 4/7/2026 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/5/2021 THOMAS LANG
BHO/Hillside ordinance Cleared 2/5/2021 THOMAS LANG
BHO/Hillside ordinance Cleared 2/5/2021 THOMAS LANG
BHO/Hillside ordinance Cleared 2/5/2021 THOMAS LANG
BHO/Hillside ordinance Cleared 2/5/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/5/2021 THOMAS LANG
Sewer availability Cleared 2/5/2021 THOMAS LANG
Hydrant and Access approval Cleared 2/11/2021 KURT CORRAL
Low Impact Development Cleared 5/27/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 7/22/2022 JEANETTE VONG
Grading Pre-Inspection Cleared 10/12/2022 ARMEN JIVALAGIAN

Contact Information

Contractor Pure Energy Construction; Lic. No.: 1066309-B 9301 CORBIN AVE STE 1900      NORTHRIDGE, CA 91324
Engineer Basso,, Alexandre; Lic. No.: C77670 7231 SUMMITROSE ST      TUJUNGA, CA 91042

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/5/2023 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 10/12/2023 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 10/16/2023 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 10/26/2023 Conditional Approval OSVALDO PARAMO
Deputy Reinf. Concrete 11/8/2023 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 11/9/2023 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 11/22/2023 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 11/29/2023 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 1/8/2024 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 1/10/2024 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 1/10/2024 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 2/9/2024 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/8/2024 Partial Approval ALIZAH MAYAGOITIA
Deputy Reinf. Concrete 3/11/2024 Conditional Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 3/22/2024 Approved JOSEPH MCGARRY
Deputy Drilled-In Anchors 3/22/2024 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/22/2024 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 4/1/2024 Conditional Approval OSVALDO PARAMO
Underground Mechanical 4/1/2024 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/5/2024 Partial Approval CRAIG VAUGHAN
Deputy Steel/Welding 10/15/2024 Conditional Approval OSVALDO PARAMO
Deputy Wood Construction 1/14/2025 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 1/17/2025 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 1/17/2025 Approved OSVALDO PARAMO
Green Building Rough 1/17/2025 Not Ready for Inspection OSVALDO PARAMO
MERV13>=Rough 1/17/2025 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 3/11/2025 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 3/11/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 3/11/2025 Corrections Issued LILIANA PORTILLO
Wood Frame 3/11/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 3/21/2025 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 3/21/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 3/21/2025 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 3/21/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/7/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 4/7/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 4/7/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/11/2025 Approved ALIZAH MAYAGOITIA
Insulation 4/14/2025 Approved ANTHONY RAMOS
Drywall Nailing 5/1/2025 Approved ANTHONY RAMOS
Shower Pan 6/18/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/23/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 8/4/2025 Approved ALIZAH MAYAGOITIA
Final 10/10/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/10/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 10/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 10/10/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 10/10/2025 Approved ALIZAH MAYAGOITIA
Final 11/12/2025 Corrections Issued ALIZAH MAYAGOITIA
Final 3/31/2026 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 3/31/2026 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Approved ALIZAH MAYAGOITIA
Final 4/2/2026 OK to Issue CofO RONNIE MEDINA