648 W AMADOR ST 90012
Certificate Information: 648 W AMADOR ST 90012
- Application / Permit
- 20016-10000-28980
- Plan Check / Job No.
- B20LA20876
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION TO EXISTING SINGLE FAMILY DWELLING INCLUDING ASSOCIATED STRUCTURAL UPGRADES,ATTIC CONVERSION AND INCREASING THE PITCH ON PORTION OF THE ROOF.
- Permit Issued
- Issued on 5/30/2023
- Issuing Office
- Current Status
- CofO Issued on 4/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | ARMEN JIVALAGIAN |
| Corrections Issued | 12/24/2020 | ARMEN JIVALAGIAN |
| Quality Review Completed | 12/29/2020 | PETER KIM |
| Building Plans Picked Up | 1/6/2021 | APPLICANT |
| Applicant returned to address corrections | 2/10/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 2/24/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 5/5/2021 | ARMEN JIVALAGIAN |
| Plan Check Approved | 12/15/2022 | ARMEN JIVALAGIAN |
| Issued | 5/30/2023 | APPLICANT |
| CofO in Progress | 4/3/2026 | RONNIE MEDINA |
| Permit Finaled | 4/7/2026 | DEROLD HAUFF |
| CofO Issued | 4/7/2026 | DEROLD HAUFF |
| Permit Finaled | 4/7/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/5/2021 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 2/5/2021 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 2/5/2021 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 2/5/2021 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 2/5/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2021 | THOMAS LANG |
| Sewer availability | Cleared | 2/5/2021 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 2/11/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 5/27/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/22/2022 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 10/12/2022 | ARMEN JIVALAGIAN |
Contact Information
| Contractor | Pure Energy Construction; Lic. No.: 1066309-B | 9301 CORBIN AVE STE 1900 NORTHRIDGE, CA 91324 |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/5/2023 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 10/12/2023 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 10/16/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 10/26/2023 | Conditional Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 11/8/2023 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 11/9/2023 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 11/22/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 11/29/2023 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 1/8/2024 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 1/10/2024 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/10/2024 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 2/9/2024 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/8/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Reinf. Concrete | 3/11/2024 | Conditional Approval | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 3/22/2024 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 3/22/2024 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/22/2024 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 4/1/2024 | Conditional Approval | OSVALDO PARAMO |
| Underground Mechanical | 4/1/2024 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 4/5/2024 | Partial Approval | CRAIG VAUGHAN |
| Deputy Steel/Welding | 10/15/2024 | Conditional Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 1/14/2025 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/17/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Approved | OSVALDO PARAMO |
| Green Building Rough | 1/17/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| MERV13>=Rough | 1/17/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 3/11/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 3/11/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 3/11/2025 | Corrections Issued | LILIANA PORTILLO |
| Wood Frame | 3/11/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/21/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 3/21/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 3/21/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/21/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/7/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/7/2025 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 4/7/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/11/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 4/14/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 5/1/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 6/18/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/23/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/4/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/10/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 10/10/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 10/10/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Final | 10/10/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 10/10/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 11/12/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 3/31/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 3/31/2026 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/31/2026 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 4/2/2026 | OK to Issue CofO | RONNIE MEDINA |