7130 N FULTON AVE 91605
Certificate Information: 7130 N FULTON AVE 91605
- Application / Permit
- 20016-10000-28902
- Plan Check / Job No.
- B20LA20824
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: (N) 2-SPECIAL CANTILEVERED COLUMNS.
- Permit Issued
- Issued on 2/8/2021
- Issuing Office
- Current Status
- CofC Issued on 6/18/2021
Permit Application Status History
| Submitted | 11/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2020 | VARAND SARKISIAN |
| Corrections Issued | 12/14/2020 | VARAND SARKISIAN |
| Quality Review Completed | 12/15/2020 | DAVID CHANG |
| Plan Check Approved | 1/21/2021 | VARAND SARKISIAN |
| Issued | 2/8/2021 | APPLICANT |
| OK for CofC | 5/17/2021 | KENNETH ROBERTS |
| CofC Issued | 6/18/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 2/4/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/16/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 3/18/2021 | Partial Approval | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 3/25/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 3/25/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 3/26/2021 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 3/26/2021 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 3/26/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 3/26/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 3/30/2021 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 3/30/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 3/30/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 3/30/2021 | Approved | JOE VELASQUEZ |
| Insulation | 4/1/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 4/5/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 4/6/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 5/5/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/5/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 5/5/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 5/17/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 5/17/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 5/17/2021 | Approved | KENNETH ROBERTS |