555 S FLOWER ST 760-780 90071
Certificate Information: 555 S FLOWER ST 760-780 90071
- Application / Permit
- 20016-10000-28897
- Plan Check / Job No.
- B20LA20821
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT OF 6,602 SF OF OFFICE SPACE ON THE 7TH FLOOR NO STRUCTURAL WORK (SUITES 760, 770, 780)
- Permit Issued
- Issued on 1/15/2021
- Issuing Office
- Current Status
- Permit Finaled on 10/27/2021
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | GEORGE ALVAREZ |
| Corrections Issued | 11/23/2020 | GEORGE ALVAREZ |
| Plan Check Approved | 12/27/2020 | SINA KHOSRAVI |
| Issued | 1/15/2021 | APPLICANT |
| Building Plans Picked Up | 1/22/2021 | APPLICANT |
| Permit Finaled | 10/28/2021 | KATY RAMIREZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Riveire,, Richard Williams; Lic. No.: C22285 | 3109 N BEACHWOOD DR HOLLYWOOD, CA 90068 |
| Contractor | Phoenix Construction And Management Inc; Lic. No.: 815136-B | 515 S FLOWER STREET, STE 1270 LOS ANGELES, CA 90071 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 2/16/2021 | Corrections Issued | KATY RAMIREZ |
| Drywall Nailing | 2/24/2021 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 3/10/2021 | Partial Approval | KATY RAMIREZ |
| T-Bar Ceiling | 3/30/2021 | Approved | DANIEL COLLINS |
| T-Bar Ceiling | 3/31/2021 | Approved | DANIEL COLLINS |
| Final | 4/26/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Final | 4/26/2021 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 4/26/2021 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 4/26/2021 | Approved | KATY RAMIREZ |
| Final | 7/7/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Final | 7/7/2021 | Approved | KATY RAMIREZ |
| Final | 7/28/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 10/28/2021 | Permit Finaled | KATY RAMIREZ |