9708 S CENTRAL AVE Unit A-E 90002

Certificate Information: 9708 S CENTRAL AVE Unit A-E 90002

Application / Permit
20016-10000-28837
Plan Check / Job No.
B20LA20801
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT PORTION OF EXISTING ATTACHED GARAGE (688 sf.) TO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e) IN ONE STORY 4 UNITS APARTMENT PER ADM-2021-3315-CPIOC
Permit Issued
Issued on 11/22/2021
Issuing Office
Current Status
CofO Issued on 2/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2020 APPLICANT
Assigned to Plan Check Engineer 12/1/2020 STANLEY RAAP
Corrections Issued 12/7/2020 STANLEY RAAP
Applicant returned to address corrections 9/15/2021 RAHEL BEYENE
Applicant returned to address corrections 11/7/2021 AUNG SOE
Plan Check Approved 11/9/2021 AUNG SOE
Issued 11/22/2021 APPLICANT
Building Plans Picked Up 11/24/2021 APPLICANT
CofO in Progress 1/26/2023 ALAN MORELOS
Permit Finaled 2/6/2023 ERNESTO CORRAL
CofO Issued 2/6/2023 ERNESTO CORRAL
Permit Finaled 2/6/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 2/19/2021 CELINA MORENO
Sewer availability Cleared 2/19/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/22/2021 CELINA MORENO
Hydrant and Access approval Cleared 5/6/2021 KURT CORRAL
Community Plan Implem. Overlay Cleared 8/3/2021 HELEN JADALI
ZA Case Cleared 8/3/2021 HELEN JADALI

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/2/2022 Approved RUSSELL BONVOULOIR
Green Building Rough 6/8/2022 Approved RUSSELL BONVOULOIR
Insulation 6/8/2022 Approved RUSSELL BONVOULOIR
Wood Frame 6/8/2022 Partial Inspection RUSSELL BONVOULOIR
Wood Frame 6/14/2022 Partial Approval JAMES POWERS
Drywall Nailing 6/24/2022 Approved JAMES POWERS
Interior/Exterior Lathing 6/28/2022 Approved RUSSELL BONVOULOIR
Final 12/21/2022 Conditional Approval ALAN MORELOS
Green Building Final 12/21/2022 Approved ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Approved ALAN MORELOS
Smoke Detectors 12/21/2022 Approved ALAN MORELOS
Wood Frame 12/21/2022 Approved ALAN MORELOS
Final 1/26/2023 OK to Issue CofO ALAN MORELOS