662 N HAVERFORD AVE 90272

Certificate Information: 662 N HAVERFORD AVE 90272

Application / Permit
20016-10000-28833
Plan Check / Job No.
B20LA20795
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF EXISTING TWO STORY GARAGE/ STORAGE STRUCTURE INTO ACCESSORY DWELLING UNIT& GARAGE PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 8/12/2021
Issuing Office
Current Status
CofO Issued on 5/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2020 APPLICANT
Assigned to Plan Check Engineer 11/25/2020 ZAW HAN
Building Plans Picked Up 11/25/2020 APPLICANT
Corrections Issued 11/30/2020 ZAW HAN
Applicant returned to address corrections 5/17/2021 ZAW HAN
Plan Check Approved 5/20/2021 CHIHARU SUZUKI
Issued 8/12/2021 APPLICANT
CofO in Progress 5/6/2022 ANDREW NAVE
Permit Finaled 5/16/2022 DANIEL ORRANTE
Permit Finaled 5/16/2022 DANIEL ORRANTE
CofO Issued 5/16/2022 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 12/14/2020 DINAH GARIN
Address approval Cleared 12/15/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 3/26/2021 DINAH GARIN
ZA Case Cleared 4/22/2021 RICHARD REASER
Coastal Zone Cleared 5/18/2021 MARITZA PRZEKOP
ZI Cleared 5/18/2021 MARITZA PRZEKOP

Contact Information

Architect Miller,, Jeffrey A; Lic. No.: C37366 448B ROSECRANS AVENUE      MANHATTAN BEACH, CA 90266
Contractor Saad Maher; Lic. No.: 627177-B 7641 TEXHOMA AVENUE      NORTHRIDGE, CA 91325

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/8/2021 Approved ANDREW NAVE
ELECTRICAL-Rough 10/8/2021 Partial Approval ANDREW NAVE
HVAC-Rough 10/8/2021 Approved ANDREW NAVE
PLUMBING-Rough 10/8/2021 Partial Approval ANDREW NAVE
Pre-Inspection 11/8/2021 Approved ANDREW NAVE
Gas Test 11/24/2021 Approved KRISTEN CAUSEY
Sewer 11/30/2021 Corrections Issued JUAN VALENZUELA
Sewer 12/2/2021 Approved ANDREW NAVE
Drywall Nailing 12/7/2021 Partial Approval ANDREW NAVE
PLUMBING-Rough 12/7/2021 Approved ANDREW NAVE
Underground Mechanical 12/7/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 12/13/2021 Partial Approval BRENDAN LOONEY
Special/Order Compliance 12/16/2021 Approved ANDREW NAVE
Footing/Foundation/Slab 12/27/2021 Approved ANDREW NAVE
ELECTRICAL-Rough 1/18/2022 Approved ANDREW NAVE
PLUMBING-Rough 1/18/2022 Not Ready for Inspection ANDREW NAVE
Drywall Nailing 1/24/2022 Approved ANDREW NAVE
ELECTRICAL-Final 4/11/2022 Approved ANDREW NAVE
Final 4/11/2022 Corrections Issued ANDREW NAVE
HVAC-Final 4/11/2022 Corrections Issued ANDREW NAVE
PLUMBING-Final 4/11/2022 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 4/11/2022 SGSOV Approved ANDREW NAVE
Smoke Detectors 4/11/2022 Approved ANDREW NAVE
ELECTRICAL-Final 5/6/2022 Approved ANDREW NAVE
Final 5/6/2022 OK to Issue CofO ANDREW NAVE
HVAC-Final 5/6/2022 Approved ANDREW NAVE
PLUMBING-Final 5/6/2022 Approved ANDREW NAVE