1940 W 42ND ST 90062
Certificate Information: 1940 W 42ND ST 90062
- Application / Permit
- 20016-10000-28766
- Plan Check / Job No.
- B20LA20743
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing garage to accessory dwelling unit per state law GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/13/2021
- Issuing Office
- Current Status
- Issued on 1/13/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | VU NGUYEN |
| Corrections Issued | 11/12/2020 | VU NGUYEN |
| Applicant returned to address corrections | 11/24/2020 | ARSALAN SHABESTARI |
| Plan Check Approved | 1/8/2021 | HERNAN ARREOLA |
| Issued | 1/13/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/16/2020 | CELINA MORENO |
| Sewer availability | Cleared | 11/16/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2020 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/10/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 3/18/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 4/1/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 4/1/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 4/12/2021 | Approved | SABAS ALONSO |
| Green Building Rough | 4/12/2021 | Approved | SABAS ALONSO |
| Insulation | 4/12/2021 | Corrections Issued | SABAS ALONSO |
| Insulation | 4/21/2021 | Approved | CALEB MEISTER |
| Special/Order Compliance | 4/21/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 5/7/2021 | Approved | ADAM ESCOTO |
| Pre-Inspection | 5/7/2021 | Partial Inspection | ALAN MORELOS |
| Final | 9/30/2021 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 9/30/2021 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/30/2021 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 9/30/2021 | Approved | SABAS ALONSO |
| Green Building Final | 1/10/2022 | Partial Approval | HORACE FULTZ |
| Final | 2/4/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 2/4/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/4/2022 | SGSOV Approved | SABAS ALONSO |
| Final | 2/25/2022 | Conditional Approval | HORACE FULTZ |