6320 N VAN NUYS BLVD 91401
Certificate Information: 6320 N VAN NUYS BLVD 91401
- Application / Permit
- 20016-10000-28683
- Plan Check / Job No.
- B20LA20685
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (15) Telecommunication Transmitter - wireless
- Work Description
- MODIFY WIRELESS FACILITY PER ZA 1998-79-CU-PA1: REMOVE (6) (E) ANTENNAS AND INSTALL (6) (N) ANTENNAS. INSTALL (6) (N) RRU. INSTALL (3) (N) HCS CABLES. INSTALL (1) (N) VOLTAGE BOOSTER. INSTALL (1) (N) CABINET
- Permit Issued
- Issued on 7/1/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/15/2021
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2020 | FERNANDO FLORES |
| Corrections Issued | 11/18/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 12/22/2020 | SINA KHOSRAVI |
| Applicant returned to address corrections | 1/28/2021 | CELESTE MORRIS |
| Plan Check Approved | 5/20/2021 | JESSE JIMENEZ |
| Issued | 7/1/2021 | APPLICANT |
| Building Plans Picked Up | 7/8/2021 | APPLICANT |
| Permit Finaled | 12/15/2021 | ANDREW DORSO |
Permit Application Clearance Information
| CPC | Cleared | 2/11/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 2/11/2021 | DANIEL CORONADO |
| Plan Approval | Cleared | 3/12/2021 | CLAUDE GOODING |
| ZA Case | Cleared | 3/12/2021 | CLAUDE GOODING |
| ZA Case | Cleared | 3/12/2021 | CLAUDE GOODING |
| Supp. Use District POD/CDO/TDO | Cleared | 4/19/2021 | CORREY KITCHENS |
Contact Information
| Architect | Santillan,, Michael; Lic. No.: C23337 | 832 SANTIAGO ROAD COSTA MESA, CA 92626 |
| Contractor | Velex Inc; Lic. No.: 994697-B | 2595 DALLS PKWY STE 300 FRISCO, TX 75034 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 7/23/2021 | Not Ready for Inspection | CAMERON CHABAN |
| Final | 10/12/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/12/2021 | SGSOV Not Ready | DANNY RODRIGUEZ |
| Smoke Detectors | 10/12/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 10/15/2021 | Corrections Issued | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 10/15/2021 | SGSOV Not Required | ANDREW DORSO |
| Smoke Detectors | 10/15/2021 | Approved | ANDREW DORSO |
| Wood Frame | 10/15/2021 | Approved | ANDREW DORSO |
| Final | 12/15/2021 | Permit Finaled | ANDREW DORSO |