17745 W CHATSWORTH ST 91344
Certificate Information: 17745 W CHATSWORTH ST 91344
- Application / Permit
- 20016-10000-28681
- Plan Check / Job No.
- B20LA20679
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Dental Laboratory
- Work Description
- eplan. tenant improvement to existing dental lab office, creating two dental lab office tenant suites
- Permit Issued
- Issued on 12/11/2020
- Issuing Office
- Current Status
- Permit Finaled on 1/25/2022
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2020 | MONICA RAMIREZ |
| Corrections Issued | 11/17/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 12/4/2020 | LAMAR DAVIS |
| Plan Check Approved | 12/7/2020 | MONICA RAMIREZ |
| Issued | 12/11/2020 | APPLICANT |
| Permit Finaled | 1/24/2022 | JEFFREY FULTON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Haub,, Kevin Max; Lic. No.: C24023 | 24868 APPLE STREET SUITE 201-B SANTA CLARITA, CA 91321 |
| Contractor | Safarian Construction Inc; Lic. No.: 861469-B | 20245 VIA MADRIGAL PORTER RANCH, CA 91326 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 5/19/2021 | Conditional Approval | JEFFREY FULTON |
| Light Gage Steel Frame | 7/26/2021 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 8/10/2021 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 8/10/2021 | Partial Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 9/8/2021 | Conditional Approval | JEFFREY DURAN |
| Wood Frame | 9/29/2021 | Partial Approval | KENNETH ROBERTS |
| Deputy Wood Construction | 10/13/2021 | Conditional Approval | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2021 | Corrections Issued | JEFFREY FULTON |
| T-Bar Ceiling | 12/2/2021 | Partial Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 12/6/2021 | Approved | JEFFREY FULTON |
| Final | 1/18/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 1/18/2022 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 1/18/2022 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 1/18/2022 | Approved | JEFFREY FULTON |
| Final | 1/24/2022 | Permit Finaled | JEFFREY FULTON |
| Green Building Final | 1/24/2022 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 1/24/2022 | SGSOV No Gas | JEFFREY FULTON |