533 & N FAIRFAX AVE 90036
Certificate Information: 533 & N FAIRFAX AVE 90036
- Application / Permit
- 20016-10000-28645
- Plan Check / Job No.
- B20LA20623
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ADD 19' X 48.5' IRR. TO MAKE A 2ND STORY INSIDE THE BUILDING TO BE USED AS ACCESSORY STORAGE FOR EXISTING RETAIL BUILDING, NEW OPENING TO INTERCONNECT 2 RETAIL TENANTS, TENANT IMPROVEMENT
- Permit Issued
- Issued on 5/3/2021
- Issuing Office
- Current Status
- CofO Issued on 6/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | SAM CHANG |
| Corrections Issued | 12/17/2020 | SAM CHANG |
| Quality Review Completed | 12/24/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 12/28/2020 | APPLICANT |
| Applicant returned to address corrections | 2/23/2021 | SAM CHANG |
| Applicant returned to address corrections | 3/2/2021 | SAM CHANG |
| Green Plans Picked Up | 3/10/2021 | APPLICANT |
| Plan Check Approved | 4/8/2021 | SAM CHANG |
| Issued | 5/3/2021 | APPLICANT |
| CofO in Progress | 6/3/2022 | KATY RAMIREZ |
| CofO Issued | 6/6/2022 | ERNESTO CORRAL |
| Permit Finaled | 6/6/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 3/5/2021 | SAM CHANG |
| DAS Clearance | Cleared | 3/11/2021 | SAM CHANG |
| Sewer availability | Cleared | 3/26/2021 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2021 | ELAINE LEI |
Contact Information
| Engineer | Pereira,, Neville Roy; Lic. No.: C55991 | 1224 INVERNESS DR LA CANADA FLINTRIDGE, CA 91011 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 11/23/2021 | Not Ready for Inspection | KATY RAMIREZ |
| METHANE-Rough | 11/23/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Wood Frame | 11/23/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Rough | 12/21/2021 | Not Ready for Inspection | JONATHAN QUACH |
| METHANE-Rough | 12/21/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 12/21/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Green Building Rough | 1/4/2022 | Not Ready for Inspection | JONATHAN QUACH |
| METHANE-Rough | 1/4/2022 | Approved | JONATHAN QUACH |
| Wood Frame | 1/4/2022 | Partial Approval | JONATHAN QUACH |
| Interior/Exterior Lathing | 1/12/2022 | Approved | JONATHAN QUACH |
| Drywall Nailing | 2/18/2022 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 2/23/2022 | Partial Approval | KATY RAMIREZ |
| Pre-Inspection | 3/17/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 4/18/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 4/18/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| Green Building Final | 4/18/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| Green Building Rough | 4/18/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 4/18/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| Wood Frame | 4/18/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 4/20/2022 | SGSOV Not Ready | KATY RAMIREZ |
| Smoke Detectors | 4/20/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 4/25/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Final | 4/25/2022 | Approved | KATY RAMIREZ |
| Green Building Rough | 4/25/2022 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Not Ready | KATY RAMIREZ |
| Smoke Detectors | 4/25/2022 | Partial Inspection | KATY RAMIREZ |
| Wood Frame | 4/25/2022 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 4/27/2022 | SGSOV Not Ready | KATY RAMIREZ |
| Smoke Detectors | 4/27/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 4/29/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Footing/Foundation/Slab | 4/29/2022 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 4/29/2022 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 4/29/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 6/6/2022 | OK to Issue CofO | KATY RAMIREZ |
| Footing/Foundation/Slab | 6/6/2022 | Approved | KATY RAMIREZ |
| Smoke Detectors | 6/6/2022 | Approved | KATY RAMIREZ |