21350 W LASSEN ST 91311
Certificate Information: 21350 W LASSEN ST 91311
- Application / Permit
- 20016-10000-28644
- Plan Check / Job No.
- B20LA20620
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- EXISTING WAREHOUSE WITH OFFICE TO CREATE 115 MINI-WAREHOUSE SPACES INSIDE EXISTING WAREHOUSE
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- Permit Finaled on 12/30/2022
Permit Application Status History
| Submitted | 11/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | AUNG SOE |
| Corrections Issued | 1/11/2021 | AUNG SOE |
| Disabled Access Plans Picked Up | 1/20/2021 | APPLICANT |
| Quality Review Completed | 1/26/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/3/2021 | AUNG SOE |
| Applicant returned to address corrections | 11/15/2021 | AUNG SOE |
| Plan Check Approved | 11/17/2021 | AUNG SOE |
| Building Plans Picked Up | 11/19/2021 | APPLICANT |
| Issued | 3/2/2022 | APPLICANT |
| Permit Finaled | 12/29/2022 | DEANDRE HOFFMAN |
Permit Application Clearance Information
| Green Code | Cleared | 11/2/2021 | AARON COSTA |
| DAS Clearance | Cleared | 11/17/2021 | AUNG SOE |
Contact Information
| Architect | Patankar,, Deepak Pandit; Lic. No.: C30110 | 160 SOUTH LINDEN AVE 210 SOUTH SAN FRANCISCO, CA 94080 |
| Contractor | Owner-Builder | , |
| Engineer | Collins,, Jay William; Lic. No.: C83793 | 708 BROADWAY STE 110 TACOMA, WA 98402 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 4/18/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 4/18/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Rough | 4/18/2022 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 4/18/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 4/18/2022 | Approved | JEFFREY FULTON |
| Structural Steel Frame | 4/19/2022 | Corrections Issued | JEFFREY FULTON |
| Final | 10/5/2022 | Corrections Issued | JEFFREY FULTON |
| Green Building Final | 10/5/2022 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 10/5/2022 | Approved | JEFFREY FULTON |
| Final | 12/29/2022 | Permit Finaled | DEANDRE HOFFMAN |
| Green Building Final | 12/29/2022 | Approved | DEANDRE HOFFMAN |