4417 N HOMER ST 90031

Certificate Information: 4417 N HOMER ST 90031

Application / Permit
20016-10000-28589
Plan Check / Job No.
B20LA20597
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Repair to fire damaged residence. Replace roof rafter and ceiling joist as needed.
Permit Issued
Issued on 2/19/2021
Issuing Office
Current Status
Issued on 2/19/2021

Permit Application Status History

Submitted 12/9/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 JOE VO
Corrections Issued 12/10/2020 JOE VO
Applicant returned to address corrections 1/12/2021 MONICA RAMIREZ
Applicant returned to address corrections 2/2/2021 HELEN NGUYEN
Plan Check Approved 2/11/2021 CRYSTEL MAALOUF
Issued 2/19/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/29/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 1/29/2021 CECILIO NAVARRO
HPOZ Cleared 2/8/2021 KATIE DEBIASE
Historic monument Cleared 2/8/2021 KATIE DEBIASE

Contact Information

Contractor A'S Contractor Inc; Lic. No.: 936193-B 2440 N GLASSELL ST #T      ORANGE, CA 92865
Engineer Rivera,, Mark Paul; Lic. No.: NA66864       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 5/14/2021 Corrections Issued COREY HUPP
BUILDING-Rough-Frame 6/14/2021 Corrections Issued COREY HUPP
ELECTRICAL-Rough 6/14/2021 Not Ready for Inspection COREY HUPP
HVAC-Rough 6/14/2021 Not Ready for Inspection COREY HUPP
MERV13>=Rough 6/14/2021 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 6/14/2021 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 6/30/2021 Approved COREY HUPP
HVAC-Rough 6/30/2021 Corrections Issued COREY HUPP
Interior/Exterior Lathing 6/30/2021 Corrections Issued COREY HUPP
MERV13>=Rough 6/30/2021 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 6/30/2021 Approved COREY HUPP
BUILDING-Rough-Frame 8/10/2021 Partial Approval COREY HUPP
HVAC-Rough 8/10/2021 Approved COREY HUPP
Insulation 8/26/2021 Conditional Approval SCOTT FINNILA
Drywall Nailing 9/1/2021 Conditional Approval SCOTT FINNILA
Interior/Exterior Lathing 9/1/2021 Conditional Approval SCOTT FINNILA