3335 S FIGUEROA ST MM 90007

Certificate Information: 3335 S FIGUEROA ST MM 90007

Application / Permit
20016-10000-28160
Plan Check / Job No.
B20LA20345
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) Music School or Studio
Work Description
Eplan. TENANT IMPROVEMENT AND MISCELLANEOUS ALTERATIONS IN EXISTING SCHOOL OF MUSIC OFFICE AND CLASSROOM AREAS (CONTEMPORARY WING, PIANO WING, AND LOBBY AREA) INCLUDING DEMOLITION AND INSTALLATION OF NEW WALLS, DOORS, CEILINGS, INTERIOR FINISHES,
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
Permit Finaled on 4/6/2022

Permit Application Status History

Submitted 11/2/2020 APPLICANT
Assigned to Plan Check Engineer 11/6/2020 LARRY LEE
Corrections Issued 11/6/2020 LARRY LEE
Applicant returned to address corrections 12/4/2020 HELEN NGUYEN
Plan Check Approved 12/9/2020 HELEN NGUYEN
Issued 4/22/2021 APPLICANT
Permit Finaled 4/4/2022 RUSSELL BONVOULOIR

Permit Application Clearance Information

Redevelopment Project Area Cleared 12/1/2020 DAVID URITA

Contact Information

Architect Dontje,, Jason Alan; Lic. No.: C32176 119 28TH STREET      NEWPORT BEACH, CA 92663
Contractor Olsen H C Construction Company Inc; Lic. No.: 177029-B 710 E LOS ANGELES ST      MONROVIA, CA 91016
Engineer Bishoff,, Ryan William; Lic. No.: S6250 9252 DALTON CIRCLE      WESTMINSTER, CA 92683

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/25/2021 No Access for Inspection DARRYL ARNOLD
Light Gage Steel Frame 7/2/2021 Partial Approval LEOPOLDO MENDOZA
Drywall Nailing 7/19/2021 Partial Approval LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 7/30/2021 Approved LEOPOLDO MENDOZA
Deputy Reinf. Concrete 8/3/2021 Conditional Approval LEOPOLDO MENDOZA
Light Gage Steel Frame 9/23/2021 Partial Approval LEOPOLDO MENDOZA
Drywall Nailing 10/12/2021 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 10/27/2021 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 11/4/2021 Approved TIMOTHY BUXTON
Deputy Drilled-In Anchors 12/23/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Other (see comments) 12/23/2021 Conditional Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 12/23/2021 Approved RUSSELL BONVOULOIR
T-Bar Ceiling 1/12/2022 Approved RUSSELL BONVOULOIR
Final 4/4/2022 Permit Finaled RUSSELL BONVOULOIR
Green Building Final 4/4/2022 Approved RUSSELL BONVOULOIR
SGSOV-Seismic Gas S/O Valve 4/4/2022 SGSOV Approved RUSSELL BONVOULOIR
Smoke Detectors 4/4/2022 Approved RUSSELL BONVOULOIR