1161 E 42ND PL 90011
Certificate Information: 1161 E 42ND PL 90011
- Application / Permit
- 20016-10000-28155
- Plan Check / Job No.
- B20LA20342
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install (4) Steel Special Cantilever Columns.
- Permit Issued
- Issued on 3/25/2022
- Issuing Office
- Current Status
- CofC Issued on 10/17/2022
Permit Application Status History
| Submitted | 11/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2020 | DANIEL SANJUAN |
| Corrections Issued | 11/24/2020 | DANIEL SANJUAN |
| Quality Review Completed | 12/3/2020 | DAVID CHANG |
| Plan Check Approved | 3/2/2021 | DANIEL SANJUAN |
| Issued | 3/25/2022 | APPLICANT |
| OK for CofC | 10/17/2022 | WINSTON DUNNING |
| CofC Issued | 10/17/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/22/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/13/2022 | Approved | DARRYL ARNOLD |
| Wood Frame | 4/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 5/4/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 5/10/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 5/11/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 5/11/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 5/11/2022 | Corrections Issued | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 5/16/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 6/17/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 6/17/2022 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 7/6/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 7/22/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 8/9/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 8/9/2022 | Approved | DARRYL ARNOLD |
| Final | 10/17/2022 | OK for CofC | WINSTON DUNNING |