2242 N RIDGEMONT DR 90046
Certificate Information: 2242 N RIDGEMONT DR 90046
- Application / Permit
- 20016-10000-27995
- Plan Check / Job No.
- B20LA20251
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO ADU PER 12.2 A33 C & D
- Permit Issued
- Issued on 12/6/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | DANIEL YIP |
| Corrections Issued | 12/14/2020 | STARR CHEN |
| Building Plans Picked Up | 12/17/2020 | APPLICANT |
| Quality Review Completed | 5/18/2022 | ALLEN MANALANSAN |
| Plan Check Approved | 5/18/2022 | STARR CHEN |
| Issued | 12/6/2022 | APPLICANT |
| CofO in Progress | 8/10/2023 | RAUL BARAJAS |
| Permit Finaled | 8/21/2023 | DEROLD HAUFF |
| CofO Issued | 8/21/2023 | DEROLD HAUFF |
| Permit Finaled | 8/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2022 | ANDREW SLUSSER |
| Roof/Waste drainage to street | Cleared | 1/21/2022 | ANDREW SLUSSER |
| Street Frontage | Cleared | 1/21/2022 | ANDREW SLUSSER |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2022 | DINAH GARIN |
| Private street | Cleared | 2/22/2022 | MARC WOERSCHING |
| Hydrant and Access approval | Cleared | 2/23/2022 | JOHN CONNEALLY |
| Grading Pre-Inspection | Cleared | 3/31/2022 | ALEXANDER HELFER |
| Sewer availability | Cleared | 5/9/2022 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 5/18/2022 | STARR CHEN |
Contact Information
| Contractor | Doobek Inc; Lic. No.: 980653-B | 5308 DERRY AVE I-101, 102 AGOURA HILLS, CA 91301 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/9/2022 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 12/9/2022 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/9/2022 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 1/17/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 1/17/2023 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 1/17/2023 | Approved | RAUL BARAJAS |
| Sewer | 1/17/2023 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 1/23/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 1/23/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/3/2023 | Corrections Issued | RAUL BARAJAS |
| Green Building Rough | 2/3/2023 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 2/3/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 2/13/2023 | Partial Approval | STUART CHAPMAN |
| Insulation | 2/15/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 2/24/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 4/11/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/12/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 5/12/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 5/12/2023 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 5/12/2023 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 5/12/2023 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 5/12/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/12/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 5/12/2023 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 5/12/2023 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 5/24/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 5/24/2023 | Approved | RAUL BARAJAS |
| Final | 5/24/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 5/24/2023 | Approved | RAUL BARAJAS |
| HVAC-Final | 5/24/2023 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 5/24/2023 | Approved | RAUL BARAJAS |
| Final | 8/9/2023 | OK to Issue CofO | RAUL BARAJAS |