1440 S LINCOLN BLVD 90291
Certificate Information: 1440 S LINCOLN BLVD 90291
- Application / Permit
- 20016-10000-27975
- Plan Check / Job No.
- B20LA20237
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE OF USE FROM (E) OFFICE TO RESTAURANT WITH (776 S.F) COVERED OUTDOOR DINING AREA & WITH (1800 S.F.) TAKEAOUT AREA & (640 S.F) UNCOVERES OUTDOOR DINING ARAE & INTERIOR T.I. WITH NEW STOREFRONT
- Permit Issued
- Issued on 3/22/2021
- Issuing Office
- Current Status
- CofO Issued on 6/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2020 | APPLICANT |
| Application Withdrawn | 11/5/2020 | APPLICANT |
| Re-Activate Applicaton | 11/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | GARO TELMI |
| Corrections Issued | 12/16/2020 | GARO TELMI |
| Quality Review Completed | 12/18/2020 | PETER KIM |
| Disabled Access Plans Picked Up | 1/5/2021 | APPLICANT |
| Applicant returned to address corrections | 1/11/2021 | GARO TELMI |
| Applicant returned to address corrections | 1/25/2021 | GARO TELMI |
| Green Plans Picked Up | 2/5/2021 | APPLICANT |
| Applicant returned to address corrections | 2/18/2021 | GARO TELMI |
| Plan Check Approved | 3/22/2021 | GARO TELMI |
| Issued | 3/22/2021 | APPLICANT |
| TCO Issued (Expire Date: 04-05-2022) | 10/7/2021 | HENRY BAGHDASSARIAN |
| CofO in Progress | 6/22/2022 | SORIN CIRSTOIU |
| Permit Finaled | 6/27/2022 | DAVID TSAU |
| CofO Issued | 6/27/2022 | DAVID TSAU |
| Permit Finaled | 6/27/2022 | DAVID TSAU |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 1/19/2021 | ANTHONY MAINEZ |
| Green Code | Cleared | 1/22/2021 | GARO TELMI |
| Fire Marshal Fire Life Safety | Cleared | 1/31/2021 | WILLIAM JOHNS |
| Specific Plan | Cleared | 2/17/2021 | PEDRO AYALA |
| Food Service Establishment | Cleared | 3/9/2021 | RAMESHBHAIR PATEL |
| "Q" conditions | Cleared | 3/10/2021 | LOUIS ORTEGA |
| CPC | Cleared | 3/10/2021 | LOUIS ORTEGA |
| Comm Cor/Mini-Mall | Cleared | 3/10/2021 | LOUIS ORTEGA |
| Comm Cor/Mini-Mall | Cleared | 3/10/2021 | LOUIS ORTEGA |
| Comm Cor/Mini-Mall | Cleared | 3/10/2021 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 3/10/2021 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 3/10/2021 | LOUIS ORTEGA |
| Prkng lot landscape/Water mgmt | Cleared | 3/10/2021 | LOUIS ORTEGA |
| Supp. Use District POD/CDO/TDO | Cleared | 3/10/2021 | LOUIS ORTEGA |
| ZA Case | Cleared | 3/10/2021 | LOUIS ORTEGA |
| ZA Case | Cleared | 3/10/2021 | LOUIS ORTEGA |
| ZI | Cleared | 3/10/2021 | LOUIS ORTEGA |
| DAS Clearance | Cleared | 3/16/2021 | GARO TELMI |
| Food establishment approval | Cleared | 3/22/2021 | LACDHS APPROVED |
Contact Information
| Architect | Browning,, Caitlyn Victoria; Lic. No.: C37231 | 2619 ALVIRA ST APT 1 LOS ANGELES, CA 90034 |
| Contractor | Clc Builders Inc; Lic. No.: 580175-B | 22916 ELKWOOD STREET WEST HILLS, CA 91304 |
| Engineer | Nirattisai,, Preston; Lic. No.: C85115 | 28411 ASCENT WAY SANTA CLARITA, CA 91350 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 3/24/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 4/14/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 5/12/2021 | Partial Inspection | SORIN CIRSTOIU |
| Light Gage Steel Frame | 5/19/2021 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 5/26/2021 | Partial Approval | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 6/2/2021 | Partial Approval | SORIN CIRSTOIU |
| Final | 9/16/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Green Building Final | 9/16/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 9/16/2021 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 9/16/2021 | Approved | SORIN CIRSTOIU |
| Final | 10/1/2021 | Not Ready for Inspection | TED RIES |
| Green Building Final | 10/1/2021 | Not Ready for Inspection | TED RIES |
| SGSOV-Seismic Gas S/O Valve | 10/1/2021 | SGSOV Not Ready | TED RIES |
| Final | 10/6/2021 | Not Ready for Inspection | NICK LAROCCA |
| Green Building Final | 10/6/2021 | Approved | NICK LAROCCA |
| SGSOV-Seismic Gas S/O Valve | 10/6/2021 | SGSOV Approved | NICK LAROCCA |
| Special/Order Compliance | 3/9/2022 | No Access for Inspection | JOHN DODGE |
| Final | 5/24/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 5/26/2022 | Not Ready for Inspection | GRANT WOODS |
| Final | 6/22/2022 | OK to Issue CofO | SORIN CIRSTOIU |