1918 1/2 N TAMARIND AVE 90068
Certificate Information: 1918 1/2 N TAMARIND AVE 90068
- Application / Permit
- 20016-10000-27826
- Plan Check / Job No.
- B20LA20141
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT AN (E) DETACHED 2 CAR GARAGE [23'-4" X 24'] INTO AN ACCESSORY UNIT (ADU).
- Permit Issued
- Issued on 11/18/2021
- Issuing Office
- Current Status
- CofO Issued on 4/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2020 | CRISTINA SALAZAR |
| Corrections Issued | 11/9/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 12/4/2020 | LUKE GONZALES |
| Plan Check Approved | 2/8/2021 | JESSE JIMENEZ |
| Issued | 11/18/2021 | APPLICANT |
| Building Plans Picked Up | 11/19/2021 | APPLICANT |
| CofO in Progress | 3/8/2023 | JOAQUIN GREENOUGH |
| Permit Finaled | 4/8/2023 | DEROLD HAUFF |
| CofO Issued | 4/8/2023 | DEROLD HAUFF |
| Permit Finaled | 4/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/18/2020 | JEREMY CARTER |
| Address approval | Cleared | 12/29/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 1/4/2021 | WALLIE JONG |
| Sewer availability | Cleared | 1/4/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2021 | WALLIE JONG |
| City Hist. Cultural Monument | Cleared | 1/25/2021 | LAMBERT GIESSINGER |
| Hist. Property Cntrct Mgr Appr | Cleared | 1/25/2021 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 1/25/2021 | LAMBERT GIESSINGER |
Contact Information
| Contractor | Crb And Sons Construction; Lic. No.: 972454-B | 1563 MORENO DRIVE SIMI VALLEY, CA 93063 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 12/23/2021 | Partial Approval | RAUL BARAJAS |
| Sewer | 12/23/2021 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 1/24/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/14/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 2/14/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 2/14/2022 | Approved | BRIAN SULLIVAN |
| Insulation | 2/14/2022 | Partial Approval | BRIAN SULLIVAN |
| MERV13>=Rough | 2/14/2022 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 2/22/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/14/2022 | Approved | RUBEN SALAS |
| Shower Pan | 3/14/2022 | Approved | RUBEN SALAS |
| Insulation | 4/29/2022 | Approved | BRIAN SULLIVAN |
| Final | 9/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 9/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| MERV13>=Final | 9/22/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 9/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 3/1/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 3/1/2023 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 3/1/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 3/1/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 3/7/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Approved | JOAQUIN GREENOUGH |