12436-12438 W GARBER ST 91331
Certificate Information: 12436-12438 W GARBER ST 91331
- Application / Permit
- 20016-10000-27745
- Plan Check / Job No.
- B20LA20062
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING GARAGE INTO ADU
- Permit Issued
- Issued on 8/20/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2020 | FERNANDO FLORES |
| Corrections Issued | 11/7/2020 | FERNANDO FLORES |
| Building Plans Picked Up | 11/12/2020 | APPLICANT |
| Plan Check Approved | 1/28/2021 | RAHEL BEYENE |
| Issued | 8/20/2021 | APPLICANT |
| CofO in Progress | 7/25/2023 | MICHEL ABAJAN |
| Permit Finaled | 8/30/2023 | RUBEN SALAS |
| CofO Issued | 8/30/2023 | RUBEN SALAS |
| Permit Finaled | 8/30/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2020 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 12/30/2020 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | My Town Building And Remodeling; Lic. No.: 1036847-B | 2807 W AVE M12 PALMDALE, CA 93551 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/25/2021 | Partial Inspection | MICHEL ABAJAN |
| Insulation | 10/25/2021 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/28/2021 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/29/2021 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/10/2022 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 3/10/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/10/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/21/2022 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/21/2022 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/21/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/21/2022 | Approved | MICHEL ABAJAN |
| Insulation | 7/25/2022 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/21/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/21/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/18/2022 | Partial Inspection | MICHEL ABAJAN |
| Insulation | 10/18/2022 | Corrections Issued | MICHEL ABAJAN |
| Insulation | 12/6/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/6/2022 | Approved | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 1/23/2023 | Conditional Approval | ROBERT GOLD |
| Wood Frame | 1/30/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 2/14/2023 | Approved | MICHEL ABAJAN |
| Final | 7/13/2023 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/13/2023 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/25/2023 | Approved | MICHEL ABAJAN |
| Final | 7/25/2023 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 7/25/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/25/2023 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/25/2023 | Approved | MICHEL ABAJAN |