1217-1219 1/2 E 34TH ST 90011
Certificate Information: 1217-1219 1/2 E 34TH ST 90011
- Application / Permit
- 20016-10000-27504
- Plan Check / Job No.
- B20LA19930
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- e-plan: Proposed conversion of an existing 468 SF attached (2) car garage to an accessory dwelling unit.
- Permit Issued
- Issued on 12/7/2020
- Issuing Office
- Current Status
- CofO Issued on 12/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2020 | LARRY LEE |
| Corrections Issued | 11/9/2020 | LARRY LEE |
| Applicant returned to address corrections | 12/1/2020 | MONICA RAMIREZ |
| Plan Check Approved | 12/3/2020 | JOE VO |
| Issued | 12/7/2020 | APPLICANT |
| CofO in Progress | 12/4/2021 | JOAQUIN GREENOUGH |
| Permit Finaled | 12/17/2021 | DEROLD HAUFF |
| CofO Issued | 12/17/2021 | DEROLD HAUFF |
| Permit Finaled | 12/17/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/23/2020 | WALLIE JONG |
| Sewer availability | Cleared | 11/23/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/2/2021 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 3/2/2021 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/11/2021 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 3/11/2021 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 3/11/2021 | Partial Inspection | SCOTT FINNILA |
| ELECTRICAL-Rough | 3/18/2021 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 3/18/2021 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 4/1/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 4/1/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 4/13/2021 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 4/13/2021 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 4/23/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 7/9/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 7/9/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Final | 7/9/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Rough | 7/9/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 7/9/2021 | SGSOV Not Ready | ANSON MAGLASANG |
| Smoke Detectors | 7/9/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 7/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 7/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 7/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 7/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/23/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 7/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/30/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 7/30/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 7/30/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 7/30/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/30/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 7/30/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 8/25/2021 | Corrections Issued | HORACE FULTZ |
| HVAC-Final | 8/25/2021 | Corrections Issued | HORACE FULTZ |
| PLUMBING-Final | 8/25/2021 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 9/3/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 9/3/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 9/3/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 9/3/2021 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/3/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 9/3/2021 | Approved | JOAQUIN GREENOUGH |
| Special/Order Compliance | 9/7/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/4/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 12/4/2021 | OK to Issue CofO | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 12/4/2021 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 12/4/2021 | Approved | JOAQUIN GREENOUGH |