7240 W FOOTHILL BLVD 91042

Certificate Information: 7240 W FOOTHILL BLVD 91042

Application / Permit
20016-10000-27503
Plan Check / Job No.
B20LA19929
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Produce Market
Work Description
Eplan. Change of use from retail to food market in basement, including tenant improvement.
Permit Issued
Issued on 3/2/2021
Issuing Office
Current Status
CofO Issued on 9/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2020 APPLICANT
Assigned to Plan Check Engineer 10/28/2020 HELEN NGUYEN
Corrections Issued 10/28/2020 HELEN NGUYEN
Applicant returned to address corrections 12/29/2020 HELEN NGUYEN
Applicant returned to address corrections 1/26/2021 HELEN NGUYEN
Plan Check Approved 2/15/2021 KEVIN MORALES
Issued 3/2/2021 APPLICANT
CofO in Progress 8/16/2021 ANDREW DORSO
Permit Finaled 9/10/2021 JEFFREY DURAN
CofO Issued 9/10/2021 JEFFREY DURAN
Permit Finaled 9/10/2021 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/9/2020 ABDULLAH SADOZAI
Sewer availability Cleared 12/9/2020 ABDULLAH SADOZAI
CPC Cleared 12/10/2020 DANG NGUYEN
CPC Cleared 12/10/2020 DANG NGUYEN
ZA Case Cleared 12/10/2020 DANG NGUYEN
Specific Plan Cleared 12/18/2020 CHRISTINE BUSTILLOS
Food establishment approval Cleared 1/26/2021 LACDHS APPROVED

Contact Information

No Data Available.

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 3/4/2021 Conditional Approval ANDREW DORSO
Drywall Nailing 4/5/2021 Not Ready for Inspection ANDREW DORSO
Drywall Nailing 4/23/2021 Approved DANNY RODRIGUEZ
Final 8/3/2021 Not Ready for Inspection ANDREW DORSO
Reinforced Masonry Frame 8/3/2021 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 8/3/2021 SGSOV Approved ANDREW DORSO
Smoke Detectors 8/3/2021 Approved ANDREW DORSO
Final 8/16/2021 OK to Issue CofO ANDREW DORSO