10241-10241 1/2 N AMBOY AVE 91331

Certificate Information: 10241-10241 1/2 N AMBOY AVE 91331

Application / Permit
20016-10000-27368
Plan Check / Job No.
B20LA19822
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Junior Accessory Dwelling Unit
Work Description
ePLAN: CONVERT EXISTING 13'X20 ATTACHED GRAGE TO JADU PER GCS 65852.2(e)(1)(A) AND 65852.22 AND 12.9' X 13.645' ROOM ADDITION TO (E) SFD.
Permit Issued
Issued on 2/24/2021
Issuing Office
Current Status
CofO Issued on 2/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 CRYSTEL MAALOUF
Corrections Issued 12/4/2020 CRYSTEL MAALOUF
Quality Review Completed 12/28/2020 WING SUEN
Applicant returned to address corrections 1/27/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 2/2/2021 CRYSTEL MAALOUF
Plan Check Approved 2/10/2021 CRYSTEL MAALOUF
Issued 2/24/2021 APPLICANT
CofO in Progress 1/5/2022 MICHEL ABAJAN
No Progress 1/29/2022 MICHAEL TEMPLE
CofO in Progress 1/31/2022 MICHEL ABAJAN
Permit Finaled 2/23/2022 MICHAEL SMITH
CofO Issued 2/23/2022 MICHAEL SMITH
Permit Finaled 2/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/31/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/31/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 12/31/2020 ADRIAN CASTRO
Sewer availability Cleared 12/31/2020 ADRIAN CASTRO
Clean Up Green Up Cleared 1/14/2021 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/2/2021 Approved MICHEL ABAJAN
METHANE-Barrier 3/2/2021 Approved MICHEL ABAJAN
METHANE-Subgrade 3/2/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 3/2/2021 Partial Approval MICHEL ABAJAN
Wood Frame 3/5/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 3/15/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 3/15/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 3/15/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 3/15/2021 Approved JENNIFER RABUCHIN
Sewer 3/15/2021 Approved JENNIFER RABUCHIN
Shower Pan 3/15/2021 Approved JENNIFER RABUCHIN
Insulation 3/19/2021 Approved MICHEL ABAJAN
Drywall Nailing 3/23/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/23/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/6/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/6/2021 Approved MICHEL ABAJAN
Final 5/6/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 5/6/2021 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 5/6/2021 Approved MICHEL ABAJAN
HVAC-Final 5/6/2021 Approved MICHEL ABAJAN
METHANE-Final 5/6/2021 Approved MICHEL ABAJAN
METHANE-Rough 5/6/2021 Approved MICHEL ABAJAN
PLUMBING-Final 5/6/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/6/2021 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 5/6/2021 Approved MICHEL ABAJAN
Final 12/6/2021 Corrections Issued MICHAEL TEMPLE
Green Building Final 12/6/2021 Approved MICHAEL TEMPLE
Final 1/5/2022 OK to Issue CofO MICHEL ABAJAN