10241-10241 1/2 N AMBOY AVE 91331
Certificate Information: 10241-10241 1/2 N AMBOY AVE 91331
- Application / Permit
- 20016-10000-27368
- Plan Check / Job No.
- B20LA19822
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- ePLAN: CONVERT EXISTING 13'X20 ATTACHED GRAGE TO JADU PER GCS 65852.2(e)(1)(A) AND 65852.22 AND 12.9' X 13.645' ROOM ADDITION TO (E) SFD.
- Permit Issued
- Issued on 2/24/2021
- Issuing Office
- Current Status
- CofO Issued on 2/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 12/4/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 12/28/2020 | WING SUEN |
| Applicant returned to address corrections | 1/27/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 2/2/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 2/10/2021 | CRYSTEL MAALOUF |
| Issued | 2/24/2021 | APPLICANT |
| CofO in Progress | 1/5/2022 | MICHEL ABAJAN |
| No Progress | 1/29/2022 | MICHAEL TEMPLE |
| CofO in Progress | 1/31/2022 | MICHEL ABAJAN |
| Permit Finaled | 2/23/2022 | MICHAEL SMITH |
| CofO Issued | 2/23/2022 | MICHAEL SMITH |
| Permit Finaled | 2/23/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/31/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/31/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/31/2020 | ADRIAN CASTRO |
| Clean Up Green Up | Cleared | 1/14/2021 | LAUREN PADICK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/2/2021 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 3/2/2021 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 3/2/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/2/2021 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 3/5/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/15/2021 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/15/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/15/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/15/2021 | Approved | JENNIFER RABUCHIN |
| Sewer | 3/15/2021 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 3/15/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/19/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/23/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/23/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/6/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/6/2021 | Approved | MICHEL ABAJAN |
| Final | 5/6/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 5/6/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 5/6/2021 | Approved | MICHEL ABAJAN |
| HVAC-Final | 5/6/2021 | Approved | MICHEL ABAJAN |
| METHANE-Final | 5/6/2021 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 5/6/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/6/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 5/6/2021 | Approved | MICHEL ABAJAN |
| Final | 12/6/2021 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 12/6/2021 | Approved | MICHAEL TEMPLE |
| Final | 1/5/2022 | OK to Issue CofO | MICHEL ABAJAN |