3714 W COLISEUM ST 90016
Certificate Information: 3714 W COLISEUM ST 90016
- Application / Permit
- 20016-10000-27341
- Plan Check / Job No.
- B20LA19812
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO (E) TWO-CAR GARAGE FOR NEW ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 12/8/2021
- Issuing Office
- Current Status
- CofO Issued on 12/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 11/27/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/29/2020 | LUKE GONZALES |
| Issued | 12/8/2021 | APPLICANT |
| Building Plans Picked Up | 12/13/2021 | APPLICANT |
| CofO in Progress | 11/18/2024 | BARRY HACHE |
| Permit Finaled | 12/7/2024 | DEROLD HAUFF |
| CofO Issued | 12/7/2024 | DEROLD HAUFF |
| Permit Finaled | 12/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 6/10/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 10/16/2021 | TA ANH |
| Construction near power lines | Cleared | 11/13/2021 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 11/24/2021 | JEANETTE VONG |
Contact Information
| Contractor | Ccsl Construction Inc; Lic. No.: 1053875-B | 208 14TH STREET UNIT B HUNTINGTON BEACH, CA 92648 |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2622 DORSET DR TORRANCE, CA 90503 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/1/2023 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 3/13/2023 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 3/13/2023 | Corrections Issued | ANTHONY EGSON |
| Sewer | 3/20/2023 | Partial Approval | ANTHONY EGSON |
| Underground Mechanical | 3/20/2023 | Partial Approval | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 3/22/2023 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 3/24/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/24/2023 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 4/17/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/17/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 4/27/2023 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 4/27/2023 | Partial Approval | SCOTT FINNILA |
| Special/Order Compliance | 4/28/2023 | Partial Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Partial Approval | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 10/6/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2023 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 10/6/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/8/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 11/8/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 11/8/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/5/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 12/5/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/11/2023 | Partial Approval | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/31/2024 | Approved | ANTHONY EGSON |
| Insulation | 2/29/2024 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 3/6/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 3/6/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 3/6/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 3/8/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 3/12/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 7/5/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 7/5/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 7/5/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 7/16/2024 | Approved | ANTHONY EGSON |
| Final | 7/16/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 7/16/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 7/16/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 11/15/2024 | Approved | BARRY HACHE |
| Final | 11/15/2024 | OK to Issue CofO | BARRY HACHE |