1113 S VICTORIA AVE 90019

Certificate Information: 1113 S VICTORIA AVE 90019

Application / Permit
20016-10000-27265
Plan Check / Job No.
B20LA19779
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO AN ACCESSORY DWELLING UNIT 2 OF 2
Permit Issued
Issued on 4/14/2021
Issuing Office
Current Status
CofO Issued on 8/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 LAWRENCE QUIRANTE
Corrections Issued 11/14/2020 LAWRENCE QUIRANTE
Plan Check Approved 2/10/2021 GEORGE ALVAREZ
Issued 4/14/2021 APPLICANT
Building Plans Picked Up 4/16/2021 APPLICANT
CofO in Progress 8/11/2022 SCOTT FINNILA
Permit Finaled 8/13/2022 DEROLD HAUFF
CofO Issued 8/13/2022 DEROLD HAUFF
Permit Finaled 8/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/17/2020 CELINA MORENO
Sewer availability Cleared 12/17/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/22/2020 CELINA MORENO
HPOZ Cleared 1/7/2021 AMANDA KAINER

Contact Information

Contractor Mint Leaf Construction Inc The; Lic. No.: 994908-B 314 W 58TH ST STE 160      LOS ANGELES, CA 90037
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/26/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 4/26/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 5/10/2021 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 5/13/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 6/24/2021 Not Ready for Inspection STUART CHAPMAN
FLOOD-Proofing Certificate 6/24/2021 Not Ready for Inspection STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Approved STUART CHAPMAN
METHANE-Rough 6/24/2021 Approved STUART CHAPMAN
Rough-Elec/Plmb/HVAC 6/24/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 6/30/2021 Conditional Approval STUART CHAPMAN
ELECTRICAL-Rough 6/30/2021 Approved STUART CHAPMAN
FLOOD-Proofing Certificate 6/30/2021 Not Ready for Inspection STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/30/2021 Approved STUART CHAPMAN
HVAC-Rough 6/30/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/30/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 6/30/2021 Approved STUART CHAPMAN
Wood Frame 6/30/2021 Approved STUART CHAPMAN
Insulation 7/14/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 7/14/2021 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 7/27/2021 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 10/25/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
FLOOD-Proofing Certificate 10/25/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 10/25/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 10/25/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 10/25/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 6/14/2022 Approved STUART CHAPMAN
FLOOD-Proofing Certificate 6/14/2022 Approved STUART CHAPMAN
Final 6/14/2022 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/14/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 6/14/2022 Approved STUART CHAPMAN
Final 7/15/2022 OK to Issue CofO STUART CHAPMAN