149 1/2 W 103RD ST 90003

Certificate Information: 149 1/2 W 103RD ST 90003

Application / Permit
20016-10000-27229
Plan Check / Job No.
B20LA19759
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. Convert existing detached car garage to an accessory dwelling unit per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 8/4/2021
Issuing Office
Current Status
CofO Issued on 10/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2020 APPLICANT
Assigned to Plan Check Engineer 11/18/2020 MONICA RAMIREZ
Corrections Issued 11/19/2020 MONICA RAMIREZ
Applicant returned to address corrections 1/26/2021 MONICA RAMIREZ
Plan Check Approved 7/15/2021 MONICA RAMIREZ
Issued 8/4/2021 APPLICANT
CofO in Progress 9/15/2022 ALIZAH MAYAGOITIA
Permit Finaled 10/8/2022 DEROLD HAUFF
CofO Issued 10/8/2022 DEROLD HAUFF
Permit Finaled 10/8/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/8/2021 CECILIO NAVARRO
Sewer availability Cleared 1/8/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 3/16/2021 CECILIO NAVARRO

Contact Information

No Data Available.

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/6/2021 Partial Inspection ANSON MAGLASANG
Footing/Foundation/Slab 10/15/2021 Corrections Issued EUGENE CASSIDY
Pre-Inspection 10/15/2021 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 3/17/2022 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 5/16/2022 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 6/6/2022 Not Ready for Inspection JOHN KLARIN
Green Building Rough 6/6/2022 Approved JOHN KLARIN
Insulation 6/15/2022 Approved JOHN KLARIN
Drywall Nailing 6/27/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/27/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/28/2022 Approved JOHN KLARIN
Final 7/28/2022 Corrections Issued JOHN KLARIN
Green Building Final 7/28/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 7/28/2022 SGSOV Approved JOHN KLARIN
Smoke Detectors 7/28/2022 Approved JOHN KLARIN
Final 8/29/2022 Corrections Issued ANSON MAGLASANG
Final 9/9/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 9/15/2022 OK to Issue CofO ALIZAH MAYAGOITIA