2836 1/2 S RIMPAU BLVD 90016

Certificate Information: 2836 1/2 S RIMPAU BLVD 90016

Application / Permit
20016-10000-27218
Plan Check / Job No.
B20LA19750
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU PER GCS65852.2(e)(1)(A).
Permit Issued
Issued on 8/25/2021
Issuing Office
Current Status
CofO Issued on 6/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2020 APPLICANT
Assigned to Plan Check Engineer 10/26/2020 RICARDO RAMIREZ
Corrections Issued 10/28/2020 RICARDO RAMIREZ
Applicant returned to address corrections 12/8/2020 CRISTINA SALAZAR
Applicant returned to address corrections 4/13/2021 CRISTINA SALAZAR
Applicant returned to address corrections 5/4/2021 TSE MING HUANG
Plan Check Approved 5/21/2021 TSE MING HUANG
Building Plans Picked Up 8/20/2021 APPLICANT
Issued 8/25/2021 APPLICANT
CofO in Progress 5/30/2024 JUSTIN HAWLEY
Permit Finaled 6/4/2024 DEROLD HAUFF
CofO Issued 6/4/2024 DEROLD HAUFF
Permit Finaled 6/4/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/3/2020 CELINA MORENO
Sewer availability Cleared 12/3/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/7/2020 CELINA MORENO
Hydrant and Access approval Cleared 12/15/2020 KURT CORRAL
Construction near power lines Cleared 2/16/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/9/2021 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 1/4/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 2/18/2022 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 2/18/2022 Approved STUART CHAPMAN
PLUMBING-Rough 2/18/2022 Approved STUART CHAPMAN
Insulation 4/1/2022 Partial Approval ALEJANDRO DE ARTOLA
Insulation 4/7/2022 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 4/7/2022 Partial Approval STUART CHAPMAN
Insulation 4/22/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 6/1/2022 Approved STUART CHAPMAN
Drywall Nailing 6/1/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Approved STUART CHAPMAN
Green Building Rough 6/1/2022 Approved STUART CHAPMAN
HVAC-Rough 6/1/2022 Approved STUART CHAPMAN
Underground Mechanical 8/24/2022 Partial Approval STUART CHAPMAN
PLUMBING-Rough 10/18/2022 Approved STUART CHAPMAN
Sewer 10/18/2022 Approved STUART CHAPMAN
Final 5/6/2024 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 5/6/2024 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 5/6/2024 Approved JUSTIN HAWLEY
Final 5/28/2024 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Approved JUSTIN HAWLEY
ELECTRICAL-Final 5/30/2024 Approved JUSTIN HAWLEY
Final 5/30/2024 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 5/30/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 5/30/2024 Approved JUSTIN HAWLEY