3960 N CARPENTER AVE 91604
Certificate Information: 3960 N CARPENTER AVE 91604
- Application / Permit
- 20016-10000-27044
- Plan Check / Job No.
- B20LA19639
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) GYM & REC ROOM TO TWO ATTACHED ADU UNITS PER GCS 65852.2 (E)(1)(C) FOR EXISTING 26 UNIT MULTIFAMILY BUILDING
- Permit Issued
- Issued on 7/27/2021
- Issuing Office
- Current Status
- CofO Issued on 4/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2020 | RICARDO RAMIREZ |
| Corrections Issued | 10/30/2020 | RICARDO RAMIREZ |
| Building Plans Picked Up | 11/16/2020 | APPLICANT |
| Applicant returned to address corrections | 2/4/2021 | LUKE GONZALES |
| Plan Check Approved | 7/13/2021 | RICARDO RAMIREZ |
| Issued | 7/27/2021 | APPLICANT |
| CofO in Progress | 4/11/2022 | ROBERT DAVIS |
| Permit Finaled | 4/13/2022 | JEFFREY DURAN |
| CofO Issued | 4/13/2022 | JEFFREY DURAN |
| Permit Finaled | 4/13/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 11/24/2020 | RUBEN VASQUEZ |
| Address approval | Cleared | 11/30/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/30/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 12/1/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2020 | ADRIAN CASTRO |
| Fire Marshal Fire Life Safety | Cleared | 6/29/2021 | PEJMAN NOORI |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: C37588 | 921 S HOLT AVENUE LOS ANGELES, CA 90035 |
| Contractor | Rent Ready Construction Inc; Lic. No.: 1065376-B | 631 N SIERRA BONITA AVE LOS ANGELES, CA 90036 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 11/16/2021 | Approved | ROBERT DAVIS |
| Wood Frame | 11/16/2021 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 11/23/2021 | Corrections Issued | ROBERT DAVIS |
| Drywall Nailing | 11/30/2021 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 12/10/2021 | Approved | ROBERT DAVIS |
| Light Gage Steel Frame | 1/5/2022 | Approved | ROBERT DAVIS |
| Final | 3/4/2022 | Corrections Issued | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 3/4/2022 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 3/4/2022 | Approved | ROBERT DAVIS |
| Wood Frame | 3/4/2022 | Approved | ROBERT DAVIS |
| Final | 4/11/2022 | OK to Issue CofO | ROBERT DAVIS |