3534 S MUIRFIELD ROAD 90016
Certificate Information: 3534 S MUIRFIELD ROAD 90016
- Application / Permit
- 20016-10000-27028
- Plan Check / Job No.
- B20LA19610
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) GARAGE CONVERSION INTO ADU (549 SF)
- Permit Issued
- Issued on 4/16/2021
- Issuing Office
- Current Status
- CofO Issued on 1/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2020 | TSE MING HUANG |
| Corrections Issued | 1/18/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 3/10/2021 | LUKE GONZALES |
| Plan Check Approved | 4/15/2021 | RAHEL BEYENE |
| Issued | 4/16/2021 | APPLICANT |
| Building Plans Picked Up | 4/19/2021 | APPLICANT |
| CofO in Progress | 1/25/2022 | ANTHONY EGSON |
| CofO in Progress | 3/2/2022 | ANTHONY EGSON |
| Permit Finaled | 1/11/2023 | DEROLD HAUFF |
| CofO Issued | 1/11/2023 | DEROLD HAUFF |
| Permit Finaled | 1/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 12/22/2020 | WALLIE JONG |
| Sewer availability | Cleared | 12/22/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2020 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 1/12/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 3/10/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chi,, Joseph Chiwol; Lic. No.: C53156 | 19623 BOMAR CT ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/7/2021 | Partial Approval | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 5/10/2021 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 5/12/2021 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 6/9/2021 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/9/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 6/9/2021 | Partial Approval | FREDDIE RIVERA |
| HVAC-Rough | 6/16/2021 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 6/16/2021 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 6/22/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/22/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 6/28/2021 | Conditional Approval | ALFREDO BALANDRA |
| Interior/Exterior Lathing | 6/28/2021 | Approved | ALFREDO BALANDRA |
| BUILDING-Rough-Frame | 7/12/2021 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 7/16/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Drywall Nailing | 7/19/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 7/27/2021 | Not Ready for Inspection | DAVID FEILER |
| Drywall Nailing | 7/29/2021 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 9/9/2021 | SGSOV Not Ready | DAVID FEILER |
| Final | 9/15/2021 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 9/15/2021 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 9/15/2021 | Not Ready for Inspection | DAVID FEILER |
| Final | 9/28/2021 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 9/28/2021 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 9/28/2021 | Approved | DAVID FEILER |
| Special/Order Compliance | 9/28/2021 | Partial Approval | ASHLEY THOMPSON |
| Pre-Inspection | 10/18/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Final | 10/21/2021 | Order to Comply Issued | ANTHONY EGSON |
| Final | 10/27/2021 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 11/16/2021 | Conditional Approval | ANTHONY EGSON |
| Final | 12/14/2021 | Corrections Issued | ANTHONY EGSON |
| Final | 12/27/2021 | No Access for Inspection | HORACE FULTZ |
| Final | 12/30/2021 | Conditional Approval | ANTHONY EGSON |
| Service/Power Release | 12/30/2021 | Approved | ANTHONY EGSON |
| Final | 2/10/2022 | Corrections Issued | HORACE FULTZ |
| Final | 2/28/2022 | OK to Issue CofO | ANTHONY EGSON |