3534 S MUIRFIELD ROAD 90016

Certificate Information: 3534 S MUIRFIELD ROAD 90016

Application / Permit
20016-10000-27028
Plan Check / Job No.
B20LA19610
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) GARAGE CONVERSION INTO ADU (549 SF)
Permit Issued
Issued on 4/16/2021
Issuing Office
Current Status
CofO Issued on 1/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2020 APPLICANT
Assigned to Plan Check Engineer 11/6/2020 TSE MING HUANG
Corrections Issued 1/18/2021 TSE MING HUANG
Applicant returned to address corrections 3/10/2021 LUKE GONZALES
Plan Check Approved 4/15/2021 RAHEL BEYENE
Issued 4/16/2021 APPLICANT
Building Plans Picked Up 4/19/2021 APPLICANT
CofO in Progress 1/25/2022 ANTHONY EGSON
CofO in Progress 3/2/2022 ANTHONY EGSON
Permit Finaled 1/11/2023 DEROLD HAUFF
CofO Issued 1/11/2023 DEROLD HAUFF
Permit Finaled 1/11/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/22/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 12/22/2020 WALLIE JONG
Sewer availability Cleared 12/22/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/29/2020 WALLIE JONG
Hydrant and Access approval Cleared 1/12/2021 MATTHEW CRAIG
Construction near power lines Cleared 3/10/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Chi,, Joseph Chiwol; Lic. No.: C53156 19623 BOMAR CT      ROWLAND HEIGHTS, CA 91748

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/7/2021 Partial Approval FREDDIE RIVERA
Deputy Drilled-In Anchors 5/10/2021 No Access for Inspection DAVID FEILER
Footing/Foundation/Slab 5/12/2021 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 6/9/2021 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 6/9/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 6/9/2021 Partial Approval FREDDIE RIVERA
HVAC-Rough 6/16/2021 Not Ready for Inspection DAVID FEILER
Wood Frame 6/16/2021 Partial Approval DAVID FEILER
HVAC-Rough 6/22/2021 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 6/22/2021 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 6/28/2021 Conditional Approval ALFREDO BALANDRA
Interior/Exterior Lathing 6/28/2021 Approved ALFREDO BALANDRA
BUILDING-Rough-Frame 7/12/2021 Approved JOAQUIN GREENOUGH
Drywall Nailing 7/16/2021 Corrections Issued JOAQUIN GREENOUGH
Drywall Nailing 7/19/2021 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 7/27/2021 Not Ready for Inspection DAVID FEILER
Drywall Nailing 7/29/2021 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Not Ready DAVID FEILER
Final 9/15/2021 Corrections Issued DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/15/2021 SGSOV Not Ready DAVID FEILER
Smoke Detectors 9/15/2021 Not Ready for Inspection DAVID FEILER
Final 9/28/2021 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/28/2021 SGSOV Approved DAVID FEILER
Smoke Detectors 9/28/2021 Approved DAVID FEILER
Special/Order Compliance 9/28/2021 Partial Approval ASHLEY THOMPSON
Pre-Inspection 10/18/2021 Not Ready for Inspection ADAM ESCOTO
Final 10/21/2021 Order to Comply Issued ANTHONY EGSON
Final 10/27/2021 Not Ready for Inspection ANTHONY EGSON
Final 11/16/2021 Conditional Approval ANTHONY EGSON
Final 12/14/2021 Corrections Issued ANTHONY EGSON
Final 12/27/2021 No Access for Inspection HORACE FULTZ
Final 12/30/2021 Conditional Approval ANTHONY EGSON
Service/Power Release 12/30/2021 Approved ANTHONY EGSON
Final 2/10/2022 Corrections Issued HORACE FULTZ
Final 2/28/2022 OK to Issue CofO ANTHONY EGSON