2830-2832 N CHADWICK CIR 90032
Certificate Information: 2830-2832 N CHADWICK CIR 90032
- Application / Permit
- 20016-10000-26996
- Plan Check / Job No.
- B20LA19575
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING CRAWL SPACE INTO AN ACCESSORY DWELLING UNIT (ADU)
- Permit Issued
- Issued on 3/19/2022
- Issuing Office
- Current Status
- CofO Issued on 1/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | PRANITA SHAH |
| Corrections Issued | 12/28/2020 | PRANITA SHAH |
| Quality Review Completed | 1/6/2021 | WING SUEN |
| Building Plans Picked Up | 1/11/2021 | APPLICANT |
| Applicant returned to address corrections | 6/25/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 7/2/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 7/12/2021 | PRANITA SHAH |
| Plan Check Approved | 3/17/2022 | PRANITA SHAH |
| Issued | 3/19/2022 | APPLICANT |
| CofO in Progress | 1/18/2023 | AMY COLIN |
| CofO Issued | 1/27/2023 | DEROLD HAUFF |
| Permit Finaled | 1/27/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/17/2021 | WALLIE JONG |
| Sewer availability | Cleared | 2/17/2021 | WALLIE JONG |
| "D" conditions | Cleared | 4/27/2021 | TERRI OSBORNE |
| "Q" conditions | Cleared | 4/27/2021 | TERRI OSBORNE |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2021 | WALLIE JONG |
| ZI | Cleared | 4/27/2021 | TERRI OSBORNE |
| Grading Pre-Inspection | Cleared | 7/14/2021 | PRANITA SHAH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/23/2022 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 6/28/2022 | Partial Approval | AMY COLIN |
| Insulation | 6/28/2022 | Partial Approval | AMY COLIN |
| Wood Frame | 6/28/2022 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 7/5/2022 | Partial Approval | AMY COLIN |
| Deputy Wood Construction | 7/5/2022 | Conditional Approval | AMY COLIN |
| Insulation | 7/5/2022 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 7/5/2022 | Corrections Issued | AMY COLIN |
| BUILDING-Rough-Frame | 7/15/2022 | Approved | AMY COLIN |
| Green Building Rough | 7/15/2022 | Approved | AMY COLIN |
| PLUMBING-Rough | 7/15/2022 | Partial Approval | AMY COLIN |
| ELECTRICAL-Rough | 7/25/2022 | Approved | AMY COLIN |
| HVAC-Rough | 7/25/2022 | Approved | AMY COLIN |
| Insulation | 7/25/2022 | Approved | AMY COLIN |
| Drywall Nailing | 8/1/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/1/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 12/15/2022 | Approved | AMY COLIN |
| Final | 12/15/2022 | Partial Inspection | AMY COLIN |
| Green Building Final | 12/15/2022 | Approved | AMY COLIN |
| HVAC-Final | 12/15/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 12/15/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 12/15/2022 | SGSOV Approved | AMY COLIN |
| Smoke Detectors | 12/15/2022 | Approved | AMY COLIN |
| Final | 1/11/2023 | Corrections Issued | AMY COLIN |
| Final | 1/18/2023 | OK to Issue CofO | AMY COLIN |