20431 W SCHOENBORN ST 91306
Certificate Information: 20431 W SCHOENBORN ST 91306
- Application / Permit
- 20016-10000-26991
- Plan Check / Job No.
- B20LA19571
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO AN ACCESSORY DWELLING UNIT (1200 SF MAX PER ORDINANCE)
- Permit Issued
- Issued on 6/10/2021
- Issuing Office
- Current Status
- CofO Issued on 12/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2020 | AUNG SOE |
| Corrections Issued | 11/4/2020 | AUNG SOE |
| Applicant returned to address corrections | 12/24/2020 | FERNANDO FLORES |
| Building Plans Picked Up | 1/7/2021 | APPLICANT |
| Plan Check Approved | 3/24/2021 | ADAM HEGAZI |
| Issued | 6/10/2021 | APPLICANT |
| CofO in Progress | 12/23/2021 | DAVID STEPANYAN |
| Permit Finaled | 12/27/2021 | JOHN JANSON |
| CofO Issued | 12/27/2021 | JOHN JANSON |
| Permit Finaled | 12/27/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/11/2021 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 2/12/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 2/12/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Raw Development Inc; Lic. No.: 989611-B | 4859 W SLAUSON AVENUE #377 LOS ANGELES, CA 90056 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/28/2021 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 7/2/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Sewer | 7/2/2021 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 7/2/2021 | Approved | DAVID STEPANYAN |
| Footing/Foundation/Slab | 7/12/2021 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 7/16/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 7/16/2021 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 7/26/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/9/2021 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Rough | 8/9/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 8/9/2021 | Approved | DAVID STEPANYAN |
| Wood Frame | 8/9/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 9/7/2021 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 9/7/2021 | Approved | DAVID STEPANYAN |
| Wood Frame | 9/7/2021 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 9/22/2021 | Approved | DAVID SANDOVAL |
| Insulation | 9/22/2021 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 10/8/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 10/8/2021 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Final | 12/20/2021 | Approved | DAVID STEPANYAN |
| Gas Test | 12/20/2021 | Approved | DAVID STEPANYAN |
| Green Building Final | 12/20/2021 | Approved | DAVID STEPANYAN |
| HVAC-Final | 12/20/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 12/20/2021 | Corrections Issued | DAVID STEPANYAN |
| Smoke Detectors | 12/20/2021 | Approved | DAVID STEPANYAN |
| Final | 12/22/2021 | OK to Issue CofO | DAVID STEPANYAN |
| PLUMBING-Final | 12/22/2021 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 12/22/2021 | SGSOV Approved | DAVID STEPANYAN |