2212 S PENMAR AVE 90291

Certificate Information: 2212 S PENMAR AVE 90291

Application / Permit
20016-10000-26975
Plan Check / Job No.
B20LA19558
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF PARTIAL EXISTING GARAGE TO ADU (395 SF) WITH NEW ROOFING AND REPLACEMENT OF EXISTING WINDOWS. NO CHANGES TO EXISTING FOOTPRINT. 2 OF 2
Permit Issued
Issued on 8/3/2021
Issuing Office
Current Status
CofO Issued on 3/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 CHUNG-WEN CHUANG
Corrections Issued 12/16/2020 CHUNG-WEN CHUANG
Quality Review Completed 12/30/2020 KESETE HAREGOT
Applicant returned to address corrections 1/21/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 6/24/2021 CHUNG-WEN CHUANG
Plan Check Approved 7/12/2021 CHUNG-WEN CHUANG
Issued 8/3/2021 APPLICANT
Building Plans Picked Up 8/9/2021 APPLICANT
CofO in Progress 2/28/2023 EVAN COOPER
Permit Finaled 3/1/2023 DANIEL ORRANTE
CofO Issued 3/1/2023 DANIEL ORRANTE
Permit Finaled 3/1/2023 DANIEL ORRANTE

Permit Application Clearance Information

"Q" conditions Cleared 1/12/2021 KENTON TRINH
Address approval Cleared 1/22/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 1/22/2021 CECILIO NAVARRO
Sewer availability Cleared 1/22/2021 CECILIO NAVARRO
Specific Plan Cleared 2/3/2021 PEDRO AYALA
Low Impact Development Cleared 6/3/2021 JORGE MEJIA LEMUS
Permit Cleared 7/8/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 7/9/2021 DINAH GARIN

Contact Information

Contractor Mardyks & Co Inc; Lic. No.: 1025120-B 3923 REDWOOD AVENUE      LOS ANGELES, CA 90066
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/12/2021 Partial Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 4/25/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 5/2/2022 Approved DAVID FEILER
ELECTRICAL-Rough 5/10/2022 Approved DAVID FEILER
Deputy Wood Construction 5/27/2022 Conditional Approval RICHARD STEINBACH
HVAC-Rough 5/27/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 6/7/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 6/13/2022 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/13/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/21/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 6/21/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 7/19/2022 Partial Approval DAVID FEILER
Green Building Rough 7/19/2022 Approved DAVID FEILER
Interior/Exterior Lathing 7/19/2022 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 7/25/2022 Not Ready for Inspection DAVID FEILER
Insulation 7/25/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 7/28/2022 Approved DAVID FEILER
Shower Pan 8/10/2022 Corrections Issued DAVID FEILER
Drywall Nailing 8/19/2022 Approved DAVID FEILER
Interior/Exterior Lathing 8/19/2022 Approved DAVID FEILER
Shower Pan 8/19/2022 Approved DAVID FEILER
ELECTRICAL-Final 12/14/2022 Approved EVAN COOPER
Gas Test 12/16/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/16/2022 SGSOV Approved EVAN COOPER
Service/Power Release 12/16/2022 Not Ready for Inspection EVAN COOPER
HVAC-Final 12/20/2022 Corrections Issued EVAN COOPER
Service/Power Release 1/5/2023 Not Required EVAN COOPER
HVAC-Final 1/12/2023 Approved EVAN COOPER
PLUMBING-Final 2/15/2023 Approved EVAN COOPER
Final 2/24/2023 Conditional Approval EVAN COOPER
Smoke Detectors 2/24/2023 Approved EVAN COOPER
Final 2/27/2023 OK to Issue CofO EVAN COOPER