2210 S PENMAR AVE 90291

Certificate Information: 2210 S PENMAR AVE 90291

Application / Permit
20016-10000-26974
Plan Check / Job No.
B20LA19558
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERSION OF (E) 2-STORY DUPLEX TO SFD (NO ADDITION). INTERIOR REMODEL OF EXISTING KITCHEN, BATHROOMS, MASTER SUITE, LAUNDRY ROOM. MOVE EXTERIOR STAIRS TO INTERIOR. 1 OF 2
Permit Issued
Issued on 8/3/2021
Issuing Office
Current Status
CofO Issued on 3/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 CHUNG-WEN CHUANG
Corrections Issued 12/16/2020 CHUNG-WEN CHUANG
Quality Review Completed 12/30/2020 KESETE HAREGOT
Applicant returned to address corrections 1/21/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 6/24/2021 CHUNG-WEN CHUANG
Plan Check Approved 7/12/2021 CHUNG-WEN CHUANG
Issued 8/3/2021 APPLICANT
Building Plans Picked Up 8/9/2021 APPLICANT
CofO in Progress 2/28/2023 EVAN COOPER
Permit Finaled 3/1/2023 DANIEL ORRANTE
CofO Issued 3/1/2023 DANIEL ORRANTE
Permit Finaled 3/1/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 2/3/2021 PEDRO AYALA
"Q" conditions Cleared 6/30/2021 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 7/8/2021 DINAH GARIN
Sewer availability Cleared 7/8/2021 DINAH GARIN

Contact Information

Contractor Mardyks & Co Inc; Lic. No.: 1025120-B 3923 REDWOOD AVENUE      LOS ANGELES, CA 90066
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2021 Partial Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 11/1/2021 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Partial Approval DAVID FEILER
Sewer 1/7/2022 Corrections Issued DAVID FEILER
Rough-Elec/Plmb/HVAC 1/12/2022 Corrections Issued DAVID FEILER
Underground Mechanical 1/12/2022 Partial Approval DAVID FEILER
Rough-Elec/Plmb/HVAC 1/24/2022 Partial Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 2/1/2022 Not Ready for Inspection DAVID FEILER
Wood Frame 2/16/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Approved DAVID FEILER
PLUMBING-Rough 4/25/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 5/2/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 5/4/2022 Approved DAVID FEILER
ELECTRICAL-Rough 5/10/2022 Approved DAVID FEILER
Deputy Wood Construction 5/27/2022 Conditional Approval RICHARD STEINBACH
HVAC-Rough 5/27/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 6/7/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 6/13/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/13/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/21/2022 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 7/5/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 7/19/2022 Approved DAVID FEILER
Green Building Rough 7/19/2022 Approved DAVID FEILER
Interior/Exterior Lathing 7/19/2022 Partial Approval DAVID FEILER
Insulation 7/25/2022 Approved DAVID FEILER
Shower Pan 8/10/2022 Corrections Issued DAVID FEILER
Drywall Nailing 8/19/2022 Approved DAVID FEILER
Interior/Exterior Lathing 8/19/2022 Approved DAVID FEILER
Shower Pan 8/19/2022 Approved DAVID FEILER
Deck 10/5/2022 Approved DAVID FEILER
Footing/Foundation/Slab 10/11/2022 Partial Inspection DAVID FEILER
Underground Mechanical 10/18/2022 Not Ready for Inspection DAVID FEILER
Underground Mechanical 10/20/2022 Partial Approval ANDREW NAVE
HVAC-Rough 11/10/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 12/14/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/14/2022 SGSOV Not Ready EVAN COOPER
Smoke Detectors 12/14/2022 Approved EVAN COOPER
Gas Test 12/16/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/16/2022 SGSOV Approved EVAN COOPER
Service/Power Release 12/16/2022 Not Ready for Inspection EVAN COOPER
HVAC-Final 12/20/2022 Corrections Issued EVAN COOPER
Service/Power Release 1/5/2023 Approved EVAN COOPER
HVAC-Final 1/12/2023 Approved EVAN COOPER
PLUMBING-Final 2/15/2023 Approved EVAN COOPER
Final 2/24/2023 Conditional Approval EVAN COOPER
Final 2/27/2023 OK to Issue CofO EVAN COOPER