8244 N REDBUSH LANE 91402

Certificate Information: 8244 N REDBUSH LANE 91402

Application / Permit
20016-10000-26910
Plan Check / Job No.
B20LA19518
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Conversion of an (E) detached 2-car garage into an accessory dwelling unit per ordinance.
Permit Issued
Issued on 2/3/2021
Issuing Office
Current Status
CofO Issued on 10/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2020 APPLICANT
Assigned to Plan Check Engineer 11/4/2020 JOE VO
Corrections Issued 11/4/2020 JOE VO
Applicant returned to address corrections 11/24/2020 JOE VO
Plan Check Approved 1/27/2021 MONICA RAMIREZ
No Progress 1/27/2021 MONICA RAMIREZ
Plan Check Approved 2/3/2021 MONICA RAMIREZ
Issued 2/3/2021 APPLICANT
CofO in Progress 6/29/2021 GREGG CUMMINGS
CofO Issued 10/5/2021 MICHAEL SMITH
Permit Finaled 10/5/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/17/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/17/2020 ADRIAN CASTRO
Sewer availability Cleared 11/17/2020 ADRIAN CASTRO
Construction near power lines Cleared 1/22/2021 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/11/2021 Approved GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 2/22/2021 Approved GREGG CUMMINGS
Footing/Foundation/Slab 2/22/2021 Approved GREGG CUMMINGS
PLUMBING-Rough 2/22/2021 Partial Approval GREGG CUMMINGS
Sewer 2/22/2021 Approved GREGG CUMMINGS
Underground Mechanical 2/22/2021 Approved GREGG CUMMINGS
Deputy Drilled-In Anchors 2/24/2021 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 3/4/2021 SGSOV Approved GREGG CUMMINGS
Underground Mechanical 3/4/2021 Corrections Issued GREGG CUMMINGS
Underground Mechanical 3/10/2021 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 3/24/2021 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 3/24/2021 Approved GREGG CUMMINGS
Green Building Rough 3/24/2021 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 3/24/2021 Approved GREGG CUMMINGS
Shower Pan 3/24/2021 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 5/3/2021 Approved GREGG CUMMINGS
Green Building Rough 5/3/2021 Approved GREGG CUMMINGS
HVAC-Rough 5/3/2021 Approved GREGG CUMMINGS
Insulation 5/6/2021 Approved MORRIS JACKSON
Pre-Inspection 5/6/2021 Partial Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/11/2021 Partial Approval GREGG CUMMINGS
Drywall Nailing 5/17/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 5/17/2021 Approved ALAN MORELOS
Final 6/23/2021 Corrections Issued GREGG CUMMINGS
Green Building Final 6/23/2021 Approved GREGG CUMMINGS
Smoke Detectors 6/23/2021 Approved GREGG CUMMINGS
ELECTRICAL-Final 6/29/2021 Approved GREGG CUMMINGS
Final 6/29/2021 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 6/29/2021 Approved GREGG CUMMINGS
PLUMBING-Final 6/29/2021 Approved GREGG CUMMINGS