7240 N FULTON AVE 91605

Certificate Information: 7240 N FULTON AVE 91605

Application / Permit
20016-10000-26760
Plan Check / Job No.
B20LA19410
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Manufacturing
Work Description
INTERIOR RENOVATION OF BUILDING AND CHANGE OF USE PORTION OF (E) STORAGE/MANUFACTURING TO MUSIC STUDIO.
Permit Issued
Issued on 4/26/2021
Issuing Office
Current Status
CofO Issued on 6/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2021 APPLICANT
Assigned to Plan Check Engineer 1/12/2021 FARSHAD ALIMOHAMADI
Corrections Issued 1/12/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 3/17/2021 LUKE GONZALES
Building Plans Picked Up 3/19/2021 APPLICANT
Plan Check Approved 4/21/2021 GARO TELMI
Issued 4/26/2021 APPLICANT
CofO in Progress 5/13/2022 ANDREW DORSO
CofO Issued 6/7/2022 JEFFREY DURAN
Permit Finaled 6/7/2022 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/21/2021 GABRIEL ROBLES
Sewer availability Cleared 4/21/2021 GABRIEL ROBLES

Contact Information

Architect Oberle,, Christopher Lee; Lic. No.: C31690 PO BOX 67      KINGS BEACH, CA 96143
Contractor Progressive Designs Inc; Lic. No.: 724660-B 13808 SATICOY STREET      PANORAMA CITY, CA 91402
Engineer Yamini,, Soly; Lic. No.: C33719 540 WARNER AVE      LOS ANGELES, CA 90024

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/29/2021 Conditional Approval ANDREW DORSO
Excavation/Setback/Form/Re-Bar 5/5/2021 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 6/2/2021 Not Ready for Inspection ANDREW DORSO
Masonry Wall/Backfill 6/2/2021 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 6/3/2021 Partial Inspection ANDREW DORSO
Masonry Wall/Backfill 6/3/2021 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 6/17/2021 Partial Inspection ANDREW DORSO
Reinforced Masonry Frame 6/17/2021 Approved ANDREW DORSO
Footing/Foundation/Slab 7/8/2021 Partial Inspection ANDREW DORSO
Wood Frame 7/8/2021 Partial Inspection ANDREW DORSO
Wood Frame 9/13/2021 Approved ANDREW DORSO
Insulation 9/17/2021 Approved ANDREW DORSO
Drywall Nailing 9/30/2021 Approved ANDREW DORSO
Light Gage Steel Frame 11/1/2021 Approved ANDREW DORSO
Final 2/16/2022 Not Ready for Inspection ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 2/16/2022 SGSOV Approved ANDREW DORSO
Smoke Detectors 2/16/2022 Not Ready for Inspection ANDREW DORSO
Final 5/13/2022 OK to Issue CofO ANDREW DORSO
Smoke Detectors 5/13/2022 Approved ANDREW DORSO