2238 S PARNELL AVE 90064
Certificate Information: 2238 S PARNELL AVE 90064
- Application / Permit
- 20016-10000-26707
- Plan Check / Job No.
- B20LA19379
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERT EXISTING DETACHED GARAGE/STORAGE TO ADU
- Permit Issued
- Issued on 9/23/2021
- Issuing Office
- Current Status
- CofO Issued on 1/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 11/4/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 1/5/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 1/13/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 2/17/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 2/18/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 2/22/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 3/2/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 3/9/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 6/24/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 8/23/2021 | CARLOS MONTES |
| Plan Check Approved | 9/8/2021 | ARSALAN SHABESTARI |
| Issued | 9/23/2021 | APPLICANT |
| CofO in Progress | 1/13/2025 | STEPHANIE SWANSON |
| Permit Finaled | 1/15/2025 | RICHARD STEINBACH |
| CofO Issued | 1/15/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/15/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2021 | DINAH GARIN |
| Sewer availability | Cleared | 1/21/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2021 | DINAH GARIN |
| Specific Plan | Cleared | 2/4/2021 | WESTON PRINGLE |
| Construction near power lines | Cleared | 5/25/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/25/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/19/2023 | Partial Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 6/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 6/14/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 6/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 7/19/2024 | Conditional Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/5/2024 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 8/5/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 8/5/2024 | Partial Approval | SEAN HAUPT |
| HVAC-Rough | 8/5/2024 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 8/5/2024 | Approved | SEAN HAUPT |
| Insulation | 8/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/12/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 8/12/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 8/12/2024 | Approved | STEPHANIE SWANSON |
| Sewer | 8/12/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 8/19/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 9/20/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 9/24/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 1/9/2025 | Corrections Issued | BOBBY KEY |
| Final | 1/9/2025 | Corrections Issued | BOBBY KEY |
| Green Building Final | 1/9/2025 | Approved | BOBBY KEY |
| HVAC-Final | 1/9/2025 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 1/9/2025 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/9/2025 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 1/9/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/13/2025 | Approved | STEPHANIE SWANSON |
| Final | 1/13/2025 | OK to Issue CofO | STEPHANIE SWANSON |
| HVAC-Final | 1/13/2025 | Approved | STEPHANIE SWANSON |