5899 W VENICE BLVD 90019

Certificate Information: 5899 W VENICE BLVD 90019

Application / Permit
20016-10000-26690
Plan Check / Job No.
B20LA19357
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(6) Church
Work Description
CANOPY ADDITON BETWEEN 2 BUILDING, RESTROOM + ACCESSIBILITY UPGRADES. INTERIOR UPGRADES TO RECEPTION/SECRUITY AREA. ASSEMBLY SPACE STOREFRONT REPLACEMENT AND HARD-SCAPE UPGRADES.
Permit Issued
Issued on 6/16/2021
Issuing Office
Current Status
Permit Finaled on 5/13/2022

Permit Application Status History

Submitted 11/2/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 HERNAN ARREOLA
Corrections Issued 11/20/2020 HERNAN ARREOLA
Quality Review Completed 11/25/2020 ALLEN MANALANSAN
Disabled Access Plans Picked Up 1/21/2021 APPLICANT
Applicant returned to address corrections 5/7/2021 HERNAN ARREOLA
Plan Check Approved 5/12/2021 HERNAN ARREOLA
Issued 6/16/2021 APPLICANT
Building Plans Picked Up 6/22/2021 APPLICANT
Permit Finaled 5/13/2022 KATY RAMIREZ

Permit Application Clearance Information

ZA Case Cleared 12/15/2020 ANACANY HURTADO
ZA Case Cleared 12/15/2020 ANACANY HURTADO
ZA Case Cleared 12/15/2020 ANACANY HURTADO
ZA Case Cleared 12/15/2020 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 1/20/2021 ROSA SILVA
DAS Clearance Cleared 2/4/2021 SHINE LIN
Low Impact Development Cleared 4/7/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/13/2021 ROSA SILVA
Community Plan Implem. Overlay Cleared 4/22/2021 KYLE WINSTON

Contact Information

Architect Bruce,, Thomas A; Lic. No.: C31251 1837 N WILTON PL 6      LOS ANGELES, CA 90028
Contractor Coastal Pacific Construction Inc; Lic. No.: 478584-B 28 EDELMAN      IRVINE, CA 92618
Engineer Kathuria,, Deepansh; Lic. No.: S5572 707 WILSHIRE BLVD STE 5100      LOS ANGELES, CA 90017

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 8/4/2021 Not Ready for Inspection TIMOTHY BUXTON
Light Gage Steel Frame 8/5/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 8/10/2021 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 8/13/2021 Partial Approval TIMOTHY BUXTON
Masonry Wall/Backfill 8/30/2021 Partial Approval KATY RAMIREZ
Deputy Steel/Welding 8/31/2021 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Masonry 9/1/2021 Conditional Approval KATY RAMIREZ
Pre-Inspection 9/15/2021 Partial Inspection KATY RAMIREZ
Deputy Reinf. Masonry 9/20/2021 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 9/27/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 9/27/2021 Partial Approval KATY RAMIREZ
Deputy Reinf. Masonry 9/28/2021 Conditional Approval KATY RAMIREZ
Footing/Foundation/Slab 10/21/2021 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 10/22/2021 Partial Approval KATY RAMIREZ
Wood Frame 11/9/2021 Partial Inspection KATY RAMIREZ
Deputy Reinf. Concrete 11/10/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/12/2021 Conditional Approval KATY RAMIREZ
Wood Frame 12/23/2021 Not Ready for Inspection TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 12/27/2021 Approved JONATHAN QUACH
T-Bar Ceiling 12/27/2021 Approved JONATHAN QUACH
Wood Frame 12/27/2021 Approved JONATHAN QUACH
Interior/Exterior Lathing 1/11/2022 Approved EDWIN GREGORYONA
Final 3/3/2022 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 3/3/2022 Approved KATY RAMIREZ
Final 3/10/2022 Not Ready for Inspection KATY RAMIREZ
Final 5/13/2022 Permit Finaled KATY RAMIREZ