6521 N BABCOCK AVE 91606
Certificate Information: 6521 N BABCOCK AVE 91606
- Application / Permit
- 20016-10000-26453
- Plan Check / Job No.
- B20LA19208
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **eplan** Convert Detached Garage , Laundry and Patio Cover to ADU per LAMC 12.22 A.33(c)&(d). All work per Wood Frame Prescriptive Design.
- Permit Issued
- Issued on 4/14/2021
- Issuing Office
- Current Status
- CofO Issued on 1/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | ZAW HAN |
| Corrections Issued | 11/9/2020 | ZAW HAN |
| Quality Review Completed | 11/22/2020 | TU HUA |
| Applicant returned to address corrections | 12/30/2020 | ZAW HAN |
| Plan Check Approved | 4/7/2021 | ZAW HAN |
| Issued | 4/14/2021 | APPLICANT |
| CofO in Progress | 12/2/2021 | CHRISTOPHE COCHRAN |
| Permit Finaled | 1/15/2022 | MICHAEL SMITH |
| CofO Issued | 1/15/2022 | MICHAEL SMITH |
| Permit Finaled | 1/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2020 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2020 | ABDULLAH SADOZAI |
| Roof/Waste drainage to street | Cleared | 12/3/2020 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 12/3/2020 | ABDULLAH SADOZAI |
| Green Code | Cleared | 12/30/2020 | ZAW HAN |
| Construction near power lines | Cleared | 4/2/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/2/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/17/2021 | Approved | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 5/25/2021 | Approved | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 6/3/2021 | Conditional Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 6/3/2021 | Corrections Issued | RICHARD DOCKUS |
| Underground Mechanical | 6/21/2021 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 6/22/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 8/2/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/2/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Gas Test | 8/2/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 8/2/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/2/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/12/2021 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/12/2021 | Approved | CHRISTOPHE COCHRAN |
| Gas Test | 8/12/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/12/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/12/2021 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 8/12/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Insulation | 8/18/2021 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 8/24/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 11/22/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 11/22/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 11/22/2021 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 11/22/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 11/22/2021 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2021 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 11/22/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/2/2021 | OK to Issue CofO | CHRISTOPHE COCHRAN |