6521 N BABCOCK AVE 91606

Certificate Information: 6521 N BABCOCK AVE 91606

Application / Permit
20016-10000-26453
Plan Check / Job No.
B20LA19208
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**eplan** Convert Detached Garage , Laundry and Patio Cover to ADU per LAMC 12.22 A.33(c)&(d). All work per Wood Frame Prescriptive Design.
Permit Issued
Issued on 4/14/2021
Issuing Office
Current Status
CofO Issued on 1/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 ZAW HAN
Corrections Issued 11/9/2020 ZAW HAN
Quality Review Completed 11/22/2020 TU HUA
Applicant returned to address corrections 12/30/2020 ZAW HAN
Plan Check Approved 4/7/2021 ZAW HAN
Issued 4/14/2021 APPLICANT
CofO in Progress 12/2/2021 CHRISTOPHE COCHRAN
Permit Finaled 1/15/2022 MICHAEL SMITH
CofO Issued 1/15/2022 MICHAEL SMITH
Permit Finaled 1/15/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/3/2020 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 12/3/2020 ABDULLAH SADOZAI
Roof/Waste drainage to street Cleared 12/3/2020 ABDULLAH SADOZAI
Sewer availability Cleared 12/3/2020 ABDULLAH SADOZAI
Green Code Cleared 12/30/2020 ZAW HAN
Construction near power lines Cleared 4/2/2021 RIDWAN HARDY
Construction within easement Cleared 4/2/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/17/2021 Approved MORRIS JACKSON
Deputy Drilled-In Anchors 5/25/2021 Approved KRISTEN CAUSEY
Footing/Foundation/Slab 6/3/2021 Conditional Approval RICHARD DOCKUS
PLUMBING-Rough 6/3/2021 Corrections Issued RICHARD DOCKUS
Underground Mechanical 6/21/2021 Approved RICHARD DOCKUS
Footing/Foundation/Slab 6/22/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 8/2/2021 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/2/2021 Corrections Issued CHRISTOPHE COCHRAN
Gas Test 8/2/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 8/2/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/2/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/12/2021 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/12/2021 Approved CHRISTOPHE COCHRAN
Gas Test 8/12/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/12/2021 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 8/12/2021 Approved CHRISTOPHE COCHRAN
Smoke Detectors 8/12/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Insulation 8/18/2021 Approved ALIZAH MAYAGOITIA
Drywall Nailing 8/24/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 11/22/2021 Approved CHRISTOPHE COCHRAN
Final 11/22/2021 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 11/22/2021 Approved CHRISTOPHE COCHRAN
HVAC-Final 11/22/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 11/22/2021 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 11/22/2021 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 11/22/2021 Approved CHRISTOPHE COCHRAN
Final 12/2/2021 OK to Issue CofO CHRISTOPHE COCHRAN