12941-12943 N WHEELER AVE 91342
Certificate Information: 12941-12943 N WHEELER AVE 91342
- Application / Permit
- 20016-10000-26434
- Plan Check / Job No.
- B20LA19191
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **eplan** Conversion of (E) attached garage to ADU per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/4/2021
- Issuing Office
- Current Status
- CofO Issued on 12/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2020 | ZAW HAN |
| Corrections Issued | 11/9/2020 | ZAW HAN |
| Plan Check Approved | 12/4/2020 | KEVIN MORALES |
| Issued | 1/4/2021 | APPLICANT |
| CofO in Progress | 12/14/2021 | JOHN HAYES |
| Permit Finaled | 12/29/2021 | MICHAEL SMITH |
| CofO Issued | 12/29/2021 | MICHAEL SMITH |
| Permit Finaled | 12/29/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 11/13/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/23/2021 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 8/23/2021 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/31/2021 | Approved | MISAEL ESPARZA |
| Sewer | 9/3/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 9/13/2021 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 9/22/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/23/2021 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 9/23/2021 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/13/2021 | Approved | JOHN HAYES |
| Green Building Rough | 10/13/2021 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 10/13/2021 | Approved | JOHN HAYES |
| Insulation | 10/18/2021 | Approved | JOHN HAYES |
| Drywall Nailing | 10/22/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 10/22/2021 | Approved | JOHN HAYES |
| Shower Pan | 10/22/2021 | Approved | JOHN HAYES |
| Final | 12/6/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/6/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/6/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 12/6/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/13/2021 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 12/13/2021 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/13/2021 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 12/13/2021 | Approved | JOHN HAYES |