6311 W ROMAINE ST 90038

Certificate Information: 6311 W ROMAINE ST 90038

Application / Permit
20016-10000-26430
Plan Check / Job No.
B20LA19184
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
INTERIOR RENOVATION OF 1ST & 2ND FLRS. ADD NEW STAIRS BTW 1ST & 2ND FLR. ADA ACCESS RAMP AND WHEELCHAIR LIFT. NEW EXT CANOPY. NO CHG OF USE, NO NEW AREA, NO CHG TO PARKING
Permit Issued
Issued on 4/8/2021
Issuing Office
Current Status
Permit Finaled on 1/24/2022

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 JOE VO
Corrections Issued 11/9/2020 JOE VO
Quality Review Completed 11/20/2020 MINYE PAK
Building Plans Picked Up 11/23/2020 APPLICANT
Disabled Access Plans Picked Up 11/23/2020 APPLICANT
Applicant returned to address corrections 1/19/2021 JOE VO
Green Plans Picked Up 2/5/2021 APPLICANT
Plan Check Approved 3/13/2021 JOE VO
Issued 4/8/2021 APPLICANT
Permit Finaled 1/24/2022 JONATHAN QUACH

Permit Application Clearance Information

Green Code Cleared 2/3/2021 JOE VO
DAS Clearance Cleared 2/25/2021 JOE VO

Contact Information

Architect Turkel,, Steven David; Lic. No.: C20112 P O BOX 93155      LOS ANGELES, CA 90093
Contractor Cannon Constructors South Inc; Lic. No.: 900698-B 17000 VENTURA BLVD #301      ENCINO, CA 91316
Engineer Bains,, Gagan Prit Singh; Lic. No.: S4482 222 E HUNTINGTON DR STE 235      MONROVIA, CA 91016

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/18/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 5/21/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 5/25/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 5/26/2021 Approved TIMOTHY BUXTON
Light Gage Steel Frame 5/26/2021 Partial Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 5/27/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 6/2/2021 Conditional Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 6/4/2021 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 6/4/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 6/9/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/9/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Steel/Welding 6/9/2021 Conditional Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 6/15/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Steel/Welding 6/17/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 6/21/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/22/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Steel/Welding 6/23/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 6/25/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 6/30/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 7/1/2021 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 7/16/2021 Approved RUSSELL BONVOULOIR
T-Bar Ceiling 10/12/2021 Partial Approval SORIN CIRSTOIU
Final 1/5/2022 Partial Inspection SORIN CIRSTOIU
Green Building Final 1/5/2022 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 1/5/2022 SGSOV Approved SORIN CIRSTOIU
Smoke Detectors 1/5/2022 Approved SORIN CIRSTOIU
Final 1/24/2022 Permit Finaled JONATHAN QUACH
Green Building Final 1/24/2022 Approved JONATHAN QUACH