6311 W ROMAINE ST 90038
Certificate Information: 6311 W ROMAINE ST 90038
- Application / Permit
- 20016-10000-26430
- Plan Check / Job No.
- B20LA19184
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR RENOVATION OF 1ST & 2ND FLRS. ADD NEW STAIRS BTW 1ST & 2ND FLR. ADA ACCESS RAMP AND WHEELCHAIR LIFT. NEW EXT CANOPY. NO CHG OF USE, NO NEW AREA, NO CHG TO PARKING
- Permit Issued
- Issued on 4/8/2021
- Issuing Office
- Current Status
- Permit Finaled on 1/24/2022
Permit Application Status History
| Submitted | 10/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | JOE VO |
| Corrections Issued | 11/9/2020 | JOE VO |
| Quality Review Completed | 11/20/2020 | MINYE PAK |
| Building Plans Picked Up | 11/23/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 11/23/2020 | APPLICANT |
| Applicant returned to address corrections | 1/19/2021 | JOE VO |
| Green Plans Picked Up | 2/5/2021 | APPLICANT |
| Plan Check Approved | 3/13/2021 | JOE VO |
| Issued | 4/8/2021 | APPLICANT |
| Permit Finaled | 1/24/2022 | JONATHAN QUACH |
Permit Application Clearance Information
| Green Code | Cleared | 2/3/2021 | JOE VO |
| DAS Clearance | Cleared | 2/25/2021 | JOE VO |
Contact Information
| Architect | Turkel,, Steven David; Lic. No.: C20112 | P O BOX 93155 LOS ANGELES, CA 90093 |
| Contractor | Cannon Constructors South Inc; Lic. No.: 900698-B | 17000 VENTURA BLVD #301 ENCINO, CA 91316 |
| Engineer | Bains,, Gagan Prit Singh; Lic. No.: S4482 | 222 E HUNTINGTON DR STE 235 MONROVIA, CA 91016 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/18/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 5/21/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 5/25/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 5/26/2021 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 5/26/2021 | Partial Approval | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 5/27/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 6/2/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 6/4/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 6/4/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 6/9/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 6/9/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 6/9/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 6/15/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 6/17/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 6/21/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 6/22/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 6/23/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 6/25/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 6/30/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 7/1/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 7/16/2021 | Approved | RUSSELL BONVOULOIR |
| T-Bar Ceiling | 10/12/2021 | Partial Approval | SORIN CIRSTOIU |
| Final | 1/5/2022 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Final | 1/5/2022 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 1/5/2022 | SGSOV Approved | SORIN CIRSTOIU |
| Smoke Detectors | 1/5/2022 | Approved | SORIN CIRSTOIU |
| Final | 1/24/2022 | Permit Finaled | JONATHAN QUACH |
| Green Building Final | 1/24/2022 | Approved | JONATHAN QUACH |