2337 N ROSCOMARE ROAD 90077

Certificate Information: 2337 N ROSCOMARE ROAD 90077

Application / Permit
20016-10000-26294
Plan Check / Job No.
B20LA19080
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
Change of use from take-out restaurant to Restaurant and tenant improvement (1,041 sf). Hours of operation shall be between 7:00 am and 8:00 pm.
Permit Issued
Issued on 6/28/2021
Issuing Office
Current Status
CofO Issued on 3/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 SALVADOR QUINTANILLA
Corrections Issued 11/9/2020 SALVADOR QUINTANILLA
Quality Review Completed 11/13/2020 GARO TELMI
Disabled Access Plans Picked Up 11/17/2020 APPLICANT
Plan Check Approved 6/22/2021 SALVADOR QUINTANILLA
Building Plans Picked Up 6/23/2021 APPLICANT
Issued 6/28/2021 APPLICANT
CofO in Progress 2/22/2022 PAUL DAVIDSON
Permit Finaled 3/8/2022 DAVID TSAU
CofO Issued 3/8/2022 DAVID TSAU
Permit Finaled 3/8/2022 DAVID TSAU

Permit Application Clearance Information

"Q" conditions Cleared 12/11/2020 MAXFIELD VERMY
Comm Cor/Mini-Mall Cleared 12/11/2020 MAXFIELD VERMY
ZA Case Cleared 12/11/2020 MAXFIELD VERMY
ZA Case Cleared 12/29/2020 MAXFIELD VERMY
"T" removal Cleared 1/27/2021 MAXFIELD VERMY
Miscellaneous Cleared 4/20/2021 MAXFIELD VERMY
Food establishment approval Cleared 4/27/2021 LACDHS APPROVED
DAS Clearance Cleared 4/28/2021 SALVADOR QUINTANILLA
Food Service Establishment Cleared 4/28/2021 PAWAN VERMA

Contact Information

Contractor Graystone Builders, Inc.; Lic. No.: 894514-B P O BOX 635      VENICE, CA 90294

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 6/30/2021 Corrections Issued JOHN DODGE
SGSOV-Seismic Gas S/O Valve 6/30/2021 SGSOV Not Ready JOHN DODGE
Smoke Detectors 6/30/2021 Approved JOHN DODGE
Pre-Inspection 7/9/2021 Approved PAUL DAVIDSON
Wood Frame 11/4/2021 Approved PAUL DAVIDSON
Drywall Nailing 11/9/2021 Approved PAUL DAVIDSON
Final 2/11/2022 Conditional Approval PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Approved PAUL DAVIDSON
Final 2/18/2022 OK to Issue CofO PAUL DAVIDSON