2946 N HOLLISTER AVE 90032

Certificate Information: 2946 N HOLLISTER AVE 90032

Application / Permit
20016-10000-26246
Plan Check / Job No.
B20LA17488
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO (N) ADU per GCS 65852.2(e)(1)(A) 2 of 2
Permit Issued
Issued on 8/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2020 APPLICANT
Assigned to Plan Check Engineer 10/9/2020 DANIEL YIP
Corrections Issued 10/15/2020 DANIEL YIP
Applicant returned to address corrections 2/23/2021 RICARDO RAMIREZ
Applicant returned to address corrections 2/25/2022 LUKE GONZALES
Building Plans Picked Up 3/3/2022 APPLICANT
Applicant returned to address corrections 5/20/2022 FERNANDO FLORES
Plan Check Approved 8/8/2022 JOSEPH RAFOLS
Issued 8/12/2022 APPLICANT
CofO in Progress 1/20/2026 LILIANA PORTILLO
Permit Finaled 1/21/2026 DEROLD HAUFF
CofO Issued 1/21/2026 DEROLD HAUFF
Permit Finaled 1/21/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/15/2020 RENZ SORIANO
Sewer availability Cleared 12/15/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 2/1/2021 RENZ SORIANO
Construction within easement Cleared 8/4/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/20/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 10/5/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 10/27/2023 Approved AMY COLIN
Wood Frame 12/21/2023 Partial Approval AMY COLIN
ELECTRICAL-Rough 4/12/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 4/12/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 4/17/2024 Conditional Approval LILIANA PORTILLO
Interior/Exterior Lathing 4/17/2024 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 4/22/2024 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 4/22/2024 Conditional Approval JOSEPH MCGARRY
Green Building Rough 4/22/2024 Approved JOSEPH MCGARRY
HVAC-Rough 4/22/2024 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 4/22/2024 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 4/22/2024 Partial Approval JOSEPH MCGARRY
Insulation 5/10/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 5/24/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/17/2024 Approved LILIANA PORTILLO
Sewer 7/17/2024 Approved LILIANA PORTILLO
Shower Pan 7/17/2024 Approved LILIANA PORTILLO
Underground Mechanical 2/3/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 10/10/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 10/10/2025 Not Ready for Inspection LILIANA PORTILLO
Final 10/10/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 10/10/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 10/10/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV No Gas LILIANA PORTILLO
Smoke Detectors 10/10/2025 Approved LILIANA PORTILLO
Final 1/16/2026 OK to Issue CofO LILIANA PORTILLO