738 N RADCLIFFE AVE 90272

Certificate Information: 738 N RADCLIFFE AVE 90272

Application / Permit
20016-10000-26234
Plan Check / Job No.
B20LA19059
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-PLAN: 360 SQ.FT Garage Conversion to ADU
Permit Issued
Issued on 4/30/2021
Issuing Office
Current Status
CofO Issued on 2/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 ARSALAN SHABESTARI
Corrections Issued 10/30/2020 ARSALAN SHABESTARI
Quality Review Completed 11/21/2020 PRANITA SHAH
Applicant returned to address corrections 3/13/2021 ARSALAN SHABESTARI
Plan Check Approved 4/25/2021 ARSALAN SHABESTARI
Issued 4/30/2021 APPLICANT
CofO in Progress 2/9/2022 ANDREW NAVE
Permit Finaled 2/22/2022 DANIEL ORRANTE
CofO Issued 2/22/2022 DANIEL ORRANTE
Permit Finaled 2/22/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/9/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 2/9/2021 ANTHONY MAINEZ
Sewer availability Cleared 2/9/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 4/1/2021 BRIAN OLSON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/7/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 5/14/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 5/14/2021 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 6/18/2021 No Access for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 6/18/2021 No Access for Inspection CHRISTOPHER WILSON
Green Building Rough 6/18/2021 No Access for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/29/2021 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Rough 6/29/2021 Partial Approval ANDREW NAVE
Green Building Rough 6/29/2021 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 6/29/2021 Not Ready for Inspection ANDREW NAVE
BUILDING-Rough-Frame 7/6/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 7/6/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 7/6/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 7/13/2021 Approved ANDREW NAVE
PLUMBING-Rough 7/13/2021 Approved ANDREW NAVE
BUILDING-Rough-Frame 7/19/2021 Not Ready for Inspection ANDREW NAVE
Green Building Rough 7/19/2021 Not Ready for Inspection ANDREW NAVE
BUILDING-Rough-Frame 7/20/2021 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 7/28/2021 Partial Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 7/28/2021 Approved ANDREW NAVE
HVAC-Rough 7/28/2021 Approved ANDREW NAVE
Insulation 7/28/2021 Approved ANDREW NAVE
Drywall Nailing 8/16/2021 Conditional Approval ANDREW NAVE
Interior/Exterior Lathing 8/16/2021 Partial Approval ANDREW NAVE
Shower Pan 8/16/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 9/1/2021 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/21/2021 Approved ANDREW NAVE
ELECTRICAL-Final 12/21/2021 Corrections Issued ANDREW NAVE
Final 12/21/2021 Corrections Issued ANDREW NAVE
Green Building Final 12/21/2021 Corrections Issued ANDREW NAVE
Green Building Rough 12/21/2021 Approved ANDREW NAVE
HVAC-Final 12/21/2021 Corrections Issued ANDREW NAVE
PLUMBING-Final 12/21/2021 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 12/21/2021 SGSOV Not Ready ANDREW NAVE
Smoke Detectors 12/21/2021 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 1/10/2022 Approved ANDREW NAVE
Green Building Final 1/10/2022 Approved ANDREW NAVE
HVAC-Final 1/10/2022 Approved ANDREW NAVE
PLUMBING-Final 1/10/2022 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 1/10/2022 SGSOV Not Ready ANDREW NAVE
Smoke Detectors 1/10/2022 Not Ready for Inspection ANDREW NAVE
Final 1/28/2022 Not Ready for Inspection ANDREW NAVE
Gas Test 1/28/2022 Approved ANDREW NAVE
PLUMBING-Final 1/28/2022 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 1/28/2022 SGSOV Approved ANDREW NAVE
Smoke Detectors 1/28/2022 Approved ANDREW NAVE
Final 2/9/2022 OK to Issue CofO ANDREW NAVE