738 N RADCLIFFE AVE 90272
Certificate Information: 738 N RADCLIFFE AVE 90272
- Application / Permit
- 20016-10000-26234
- Plan Check / Job No.
- B20LA19059
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-PLAN: 360 SQ.FT Garage Conversion to ADU
- Permit Issued
- Issued on 4/30/2021
- Issuing Office
- Current Status
- CofO Issued on 2/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 10/30/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/21/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 3/13/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 4/25/2021 | ARSALAN SHABESTARI |
| Issued | 4/30/2021 | APPLICANT |
| CofO in Progress | 2/9/2022 | ANDREW NAVE |
| Permit Finaled | 2/22/2022 | DANIEL ORRANTE |
| CofO Issued | 2/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 2/22/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 2/9/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 4/1/2021 | BRIAN OLSON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/7/2021 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 5/14/2021 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 5/14/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/18/2021 | No Access for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 6/18/2021 | No Access for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 6/18/2021 | No Access for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 6/29/2021 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 6/29/2021 | Partial Approval | ANDREW NAVE |
| Green Building Rough | 6/29/2021 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 6/29/2021 | Not Ready for Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 7/6/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 7/6/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 7/6/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 7/13/2021 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 7/13/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 7/19/2021 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Rough | 7/19/2021 | Not Ready for Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 7/20/2021 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2021 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 7/28/2021 | Partial Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2021 | Approved | ANDREW NAVE |
| HVAC-Rough | 7/28/2021 | Approved | ANDREW NAVE |
| Insulation | 7/28/2021 | Approved | ANDREW NAVE |
| Drywall Nailing | 8/16/2021 | Conditional Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 8/16/2021 | Partial Approval | ANDREW NAVE |
| Shower Pan | 8/16/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 9/1/2021 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 12/21/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 12/21/2021 | Corrections Issued | ANDREW NAVE |
| Final | 12/21/2021 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 12/21/2021 | Corrections Issued | ANDREW NAVE |
| Green Building Rough | 12/21/2021 | Approved | ANDREW NAVE |
| HVAC-Final | 12/21/2021 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 12/21/2021 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 12/21/2021 | SGSOV Not Ready | ANDREW NAVE |
| Smoke Detectors | 12/21/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 1/10/2022 | Approved | ANDREW NAVE |
| Green Building Final | 1/10/2022 | Approved | ANDREW NAVE |
| HVAC-Final | 1/10/2022 | Approved | ANDREW NAVE |
| PLUMBING-Final | 1/10/2022 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 1/10/2022 | SGSOV Not Ready | ANDREW NAVE |
| Smoke Detectors | 1/10/2022 | Not Ready for Inspection | ANDREW NAVE |
| Final | 1/28/2022 | Not Ready for Inspection | ANDREW NAVE |
| Gas Test | 1/28/2022 | Approved | ANDREW NAVE |
| PLUMBING-Final | 1/28/2022 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 1/28/2022 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 1/28/2022 | Approved | ANDREW NAVE |
| Final | 2/9/2022 | OK to Issue CofO | ANDREW NAVE |