953 N SYCAMORE AVE Unit 101 90038

Certificate Information: 953 N SYCAMORE AVE Unit 101 90038

Application / Permit
20016-10000-26211
Plan Check / Job No.
B20LA19037
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Beauty Shop or Parlor
Work Description
CHANGE OF USE FROM OFFICE TO NAIL SALON SPA AND INTERIOR REMODEL. INSTALL 11 NEW PEDICURE SPA. 1 WATER HEATER, 1 HAND SINK, 1 WASHER, AND 1 DRYER. (AREA OF WORK: 669 SF)
Permit Issued
Issued on 8/24/2021
Issuing Office
Current Status
CofO Issued on 12/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2020 APPLICANT
Assigned to Plan Check Engineer 11/6/2020 GEORGE ALVAREZ
Corrections Issued 11/10/2020 GEORGE ALVAREZ
Applicant returned to address corrections 12/9/2020 CRISTINA SALAZAR
Applicant returned to address corrections 7/23/2021 GEORGE ALVAREZ
Applicant returned to address corrections 7/28/2021 GEORGE ALVAREZ
Plan Check Approved 8/10/2021 GEORGE ALVAREZ
Issued 8/24/2021 APPLICANT
Building Plans Picked Up 8/30/2021 APPLICANT
TCO Issued (Expire Date: 04-25-2023) 10/27/2022 TED RIES
CofO in Progress 12/30/2022 ERNESTO CORRAL
Permit Finaled 12/30/2022 ERNESTO CORRAL
CofO Issued 12/30/2022 ERNESTO CORRAL
Permit Finaled 12/30/2022 ERNESTO CORRAL

Permit Application Clearance Information

ZA Case Cleared 1/21/2021 KENTON TRINH
ZA Case Cleared 1/21/2021 KENTON TRINH
ZI Cleared 1/21/2021 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 1/25/2021 JEANIE LAM
Sewer availability Cleared 1/25/2021 JEANIE LAM

Contact Information

Contractor Arc Alliance Retrofitting And Construction Incorporated; Lic. No.: 1030899-B 15521 MARILLA STREET      NORTH HILLS, CA 91343

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/30/2021 No Access for Inspection KATY RAMIREZ
Pre-Inspection 8/31/2021 Approved KATY RAMIREZ
Light Gage Steel Frame 11/2/2021 No Access for Inspection KATY RAMIREZ
Light Gage Steel Frame 12/21/2021 Approved JONATHAN QUACH
Drywall Nailing 1/26/2022 Corrections Issued KATY RAMIREZ
Final 9/21/2022 Corrections Issued KATY RAMIREZ
METHANE-Final 9/21/2022 Approved KATY RAMIREZ
METHANE-Rough 9/21/2022 Approved KATY RAMIREZ
Reinforced Concrete Frame 9/21/2022 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 9/21/2022 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 9/21/2022 Not Ready for Inspection KATY RAMIREZ
Smoke Detectors 10/5/2022 Not Ready for Inspection KATY RAMIREZ
Final 10/19/2022 Partial Inspection KATY RAMIREZ
Smoke Detectors 10/19/2022 Approved KATY RAMIREZ
Special/Order Compliance 12/15/2022 Not Ready for Inspection ALFREDO LOPEZ
Final 12/16/2022 Conditional Approval ALFREDO LOPEZ
Special/Order Compliance 12/16/2022 Approved ALFREDO LOPEZ