953 N SYCAMORE AVE Unit 101 90038
Certificate Information: 953 N SYCAMORE AVE Unit 101 90038
- Application / Permit
- 20016-10000-26211
- Plan Check / Job No.
- B20LA19037
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Beauty Shop or Parlor
- Work Description
- CHANGE OF USE FROM OFFICE TO NAIL SALON SPA AND INTERIOR REMODEL. INSTALL 11 NEW PEDICURE SPA. 1 WATER HEATER, 1 HAND SINK, 1 WASHER, AND 1 DRYER. (AREA OF WORK: 669 SF)
- Permit Issued
- Issued on 8/24/2021
- Issuing Office
- Current Status
- CofO Issued on 12/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2020 | GEORGE ALVAREZ |
| Corrections Issued | 11/10/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 12/9/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 7/23/2021 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 7/28/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 8/10/2021 | GEORGE ALVAREZ |
| Issued | 8/24/2021 | APPLICANT |
| Building Plans Picked Up | 8/30/2021 | APPLICANT |
| TCO Issued (Expire Date: 04-25-2023) | 10/27/2022 | TED RIES |
| CofO in Progress | 12/30/2022 | ERNESTO CORRAL |
| Permit Finaled | 12/30/2022 | ERNESTO CORRAL |
| CofO Issued | 12/30/2022 | ERNESTO CORRAL |
| Permit Finaled | 12/30/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| ZA Case | Cleared | 1/21/2021 | KENTON TRINH |
| ZA Case | Cleared | 1/21/2021 | KENTON TRINH |
| ZI | Cleared | 1/21/2021 | KENTON TRINH |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2021 | JEANIE LAM |
| Sewer availability | Cleared | 1/25/2021 | JEANIE LAM |
Contact Information
| Contractor | Arc Alliance Retrofitting And Construction Incorporated; Lic. No.: 1030899-B | 15521 MARILLA STREET NORTH HILLS, CA 91343 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/30/2021 | No Access for Inspection | KATY RAMIREZ |
| Pre-Inspection | 8/31/2021 | Approved | KATY RAMIREZ |
| Light Gage Steel Frame | 11/2/2021 | No Access for Inspection | KATY RAMIREZ |
| Light Gage Steel Frame | 12/21/2021 | Approved | JONATHAN QUACH |
| Drywall Nailing | 1/26/2022 | Corrections Issued | KATY RAMIREZ |
| Final | 9/21/2022 | Corrections Issued | KATY RAMIREZ |
| METHANE-Final | 9/21/2022 | Approved | KATY RAMIREZ |
| METHANE-Rough | 9/21/2022 | Approved | KATY RAMIREZ |
| Reinforced Concrete Frame | 9/21/2022 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 9/21/2022 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 9/21/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Smoke Detectors | 10/5/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 10/19/2022 | Partial Inspection | KATY RAMIREZ |
| Smoke Detectors | 10/19/2022 | Approved | KATY RAMIREZ |
| Special/Order Compliance | 12/15/2022 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 12/16/2022 | Conditional Approval | ALFREDO LOPEZ |
| Special/Order Compliance | 12/16/2022 | Approved | ALFREDO LOPEZ |