3998 S WESTSIDE AVE 90008
Certificate Information: 3998 S WESTSIDE AVE 90008
- Application / Permit
- 20016-10000-26207
- Plan Check / Job No.
- B20LA19032
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 4/6/2021
- Issuing Office
- Current Status
- CofO Issued on 1/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2020 | GEORGE ALVAREZ |
| Corrections Issued | 10/26/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 3/11/2021 | ZAW HAN |
| Plan Check Approved | 3/16/2021 | ZAW HAN |
| Plan Check Approved | 4/6/2021 | GEORGE ALVAREZ |
| Issued | 4/6/2021 | APPLICANT |
| Building Plans Picked Up | 4/16/2021 | APPLICANT |
| CofO in Progress | 9/19/2022 | ANTHONY EGSON |
| CofO Issued | 1/11/2023 | DEROLD HAUFF |
| Permit Finaled | 1/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2020 | THOMAS LANG |
| Sewer availability | Cleared | 11/19/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | THOMAS LANG |
| Construction near power lines | Cleared | 3/1/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/1/2021 | RIDWAN HARDY |
Contact Information
| Architect | , ; Lic. No.: C37675 | 434 E 4TH STREET #509 LONG BEACH, CA 90802 |
| Contractor | All In One Construction; Lic. No.: 674782-B | 1056 CYPRESS AVENUE #H LA HABRA, CA 90631 |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: C53256 | 11607 AMESTOY AVE GRANADA HILLS, CA 91344 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/16/2021 | Corrections Issued | DAVID FEILER |
| Sewer | 4/16/2021 | Not Ready for Inspection | DAVID FEILER |
| Deputy Drilled-In Anchors | 4/19/2021 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 4/30/2021 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 4/30/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Wood Frame | 4/30/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/11/2021 | Approved | DAVID FEILER |
| Sewer | 5/11/2021 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 5/11/2021 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 5/21/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2021 | Partial Approval | DAVID FEILER |
| Sewer | 5/21/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2021 | Not Ready for Inspection | DAVID FEILER |
| Insulation | 6/7/2021 | Not Ready for Inspection | DAVID FEILER |
| Underground Mechanical | 6/7/2021 | Approved | DAVID FEILER |
| PLUMBING-Rough | 6/11/2021 | Partial Approval | DAVID FEILER |
| Insulation | 6/22/2021 | Approved | BENEVA JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 6/30/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 7/12/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/3/2021 | Corrections Issued | DAVID FEILER |
| HVAC-Rough | 8/27/2021 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 9/9/2021 | Partial Inspection | DAVID FEILER |
| HVAC-Rough | 9/9/2021 | Corrections Issued | DAVID FEILER |
| Wood Frame | 9/9/2021 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 9/14/2021 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 10/19/2021 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/22/2021 | Approved | ANTHONY EGSON |
| Shower Pan | 10/22/2021 | Corrections Issued | ANTHONY EGSON |
| Shower Pan | 10/28/2021 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 11/2/2021 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2021 | No Access for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2021 | No Access for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2021 | Approved | ADAM ESCOTO |
| BUILDING-Rough-Frame | 7/12/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 7/12/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 7/12/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 7/12/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 7/12/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/12/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 7/12/2022 | Approved | ANTHONY EGSON |
| Final | 8/4/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 8/16/2022 | OK to Issue CofO | ANTHONY EGSON |