922 E CENTURY BLVD 90002

Certificate Information: 922 E CENTURY BLVD 90002

Application / Permit
20016-10000-26206
Plan Check / Job No.
B20LA19031
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 3/1/2021
Issuing Office
Current Status
CofO Issued on 5/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/27/2020 STANLEY RAAP
Corrections Issued 10/28/2020 STANLEY RAAP
Applicant returned to address corrections 1/15/2021 LUKE GONZALES
Building Plans Picked Up 1/22/2021 APPLICANT
Plan Check Approved 2/24/2021 GEORGE ALVAREZ
Issued 3/1/2021 APPLICANT
CofO in Progress 4/28/2021 EUGENE CASSIDY
Permit Finaled 5/6/2021 DEROLD HAUFF
CofO Issued 5/6/2021 DEROLD HAUFF
Permit Finaled 5/6/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/3/2020 THOMAS LANG
Sewer availability Cleared 12/3/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 12/9/2020 THOMAS LANG
Hydrant and Access approval Cleared 1/7/2021 MATTHEW CRAIG
Construction near power lines Cleared 2/10/2021 RIDWAN HARDY

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/10/2021 Partial Approval EUGENE CASSIDY
Underground Mechanical 3/10/2021 Approved EUGENE CASSIDY
Footing/Foundation/Slab 3/11/2021 Partial Approval EUGENE CASSIDY
Underground Mechanical 3/11/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/23/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 3/23/2021 Approved EUGENE CASSIDY
Green Building Rough 3/23/2021 Approved EUGENE CASSIDY
HVAC-Rough 3/23/2021 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 3/23/2021 Approved EUGENE CASSIDY
Insulation 3/25/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/26/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Approved EUGENE CASSIDY
Drywall Nailing 4/5/2021 Approved EUGENE CASSIDY
Final 4/15/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 4/15/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/15/2021 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 4/15/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 4/28/2021 Approved EUGENE CASSIDY
Final 4/28/2021 OK to Issue CofO EUGENE CASSIDY
Green Building Final 4/28/2021 Approved EUGENE CASSIDY
HVAC-Final 4/28/2021 Approved EUGENE CASSIDY
PLUMBING-Final 4/28/2021 Approved EUGENE CASSIDY
Service/Power Release 4/28/2021 Approved EUGENE CASSIDY