922 E CENTURY BLVD 90002
Certificate Information: 922 E CENTURY BLVD 90002
- Application / Permit
- 20016-10000-26206
- Plan Check / Job No.
- B20LA19031
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 3/1/2021
- Issuing Office
- Current Status
- CofO Issued on 5/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2020 | STANLEY RAAP |
| Corrections Issued | 10/28/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 1/15/2021 | LUKE GONZALES |
| Building Plans Picked Up | 1/22/2021 | APPLICANT |
| Plan Check Approved | 2/24/2021 | GEORGE ALVAREZ |
| Issued | 3/1/2021 | APPLICANT |
| CofO in Progress | 4/28/2021 | EUGENE CASSIDY |
| Permit Finaled | 5/6/2021 | DEROLD HAUFF |
| CofO Issued | 5/6/2021 | DEROLD HAUFF |
| Permit Finaled | 5/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2020 | THOMAS LANG |
| Sewer availability | Cleared | 12/3/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 1/7/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 2/10/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/10/2021 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 3/10/2021 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/11/2021 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 3/11/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/23/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 3/23/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 3/23/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 3/23/2021 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 3/23/2021 | Approved | EUGENE CASSIDY |
| Insulation | 3/25/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/26/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 4/5/2021 | Approved | EUGENE CASSIDY |
| Final | 4/15/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/15/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/15/2021 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 4/15/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/28/2021 | Approved | EUGENE CASSIDY |
| Final | 4/28/2021 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 4/28/2021 | Approved | EUGENE CASSIDY |
| HVAC-Final | 4/28/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 4/28/2021 | Approved | EUGENE CASSIDY |
| Service/Power Release | 4/28/2021 | Approved | EUGENE CASSIDY |