23263-23265 W VANOWEN ST 91307
Certificate Information: 23263-23265 W VANOWEN ST 91307
- Application / Permit
- 20016-10000-26136
- Plan Check / Job No.
- B20LA18976
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *ePLAN CHECK* CONVERT (E) ATTACHED 24'x20' GARAGE TO A.D.U. PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/29/2021
- Issuing Office
- Current Status
- CofO Issued on 4/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 11/2/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 12/4/2020 | MINYE PAK |
| Applicant returned to address corrections | 1/12/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 1/25/2021 | CRYSTEL MAALOUF |
| Issued | 1/29/2021 | APPLICANT |
| CofO in Progress | 12/2/2021 | TROY SANDERS |
| No Progress | 3/18/2023 | MICHAEL PELHAM |
| CofO in Progress | 4/22/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/22/2023 | DANIEL ORRANTE |
| CofO Issued | 4/22/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/22/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 12/1/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/19/2021 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 8/25/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 9/16/2021 | Approved | TROY SANDERS |
| HVAC-Rough | 9/16/2021 | Approved | TROY SANDERS |
| Insulation | 9/16/2021 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 9/16/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 9/27/2021 | Approved | TROY SANDERS |
| Green Building Rough | 9/27/2021 | Approved | TROY SANDERS |
| Insulation | 9/27/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 9/27/2021 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 10/5/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/5/2021 | Approved | TROY SANDERS |
| Final | 11/12/2021 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 11/12/2021 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 11/12/2021 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 11/12/2021 | Approved | SEAN HAUPT |
| Final | 11/16/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 11/16/2021 | Corrections Issued | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/16/2021 | SGSOV Not Ready | TROY SANDERS |
| Final | 11/23/2021 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 11/23/2021 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 11/23/2021 | Approved | TROY SANDERS |
| Final | 12/2/2021 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 12/2/2021 | Approved | TROY SANDERS |