2244 W 24TH ST 90018
Certificate Information: 2244 W 24TH ST 90018
- Application / Permit
- 20016-10000-26131
- Plan Check / Job No.
- B20LA18974
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: 1 (N) SCCS.
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Current Status
- CofC Issued on 3/17/2022
Permit Application Status History
| Submitted | 10/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2020 | VARAND SARKISIAN |
| Corrections Issued | 10/26/2020 | VARAND SARKISIAN |
| Quality Review Completed | 10/29/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 11/24/2020 | VARAND SARKISIAN |
| Plan Check Approved | 12/16/2020 | VARAND SARKISIAN |
| Issued | 2/19/2021 | APPLICANT |
| OK for CofC | 3/8/2022 | WINSTON DUNNING |
| CofC Issued | 3/17/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | THOMAS LANG |
| HPOZ | Cleared | 12/7/2020 | DEEPEAKA DHALIWAL |
| Tenant Habitability Plan | Cleared | 1/25/2021 | PHILLIP MUNGUIA |
Contact Information
| Engineer | Zohrevand,, Pedram; Lic. No.: NA82328 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/12/2021 | Approved | DARRYL ARNOLD |
| Pre-Inspection | 3/17/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 3/19/2021 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/19/2021 | Approved | DARRYL ARNOLD |
| Piling/Pier/Caisson | 3/19/2021 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 6/18/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 6/21/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 8/11/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 8/11/2021 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/11/2021 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 8/11/2021 | Corrections Issued | DARRYL ARNOLD |
| Special/Order Compliance | 12/27/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 3/8/2022 | OK for CofC | WINSTON DUNNING |
| METHANE-Final | 3/8/2022 | Partial Inspection | WINSTON DUNNING |
| SGSOV-Seismic Gas S/O Valve | 3/8/2022 | SGSOV Approved | WINSTON DUNNING |