23053 W COVELLO ST 91307
Certificate Information: 23053 W COVELLO ST 91307
- Application / Permit
- 20016-10000-25971
- Plan Check / Job No.
- B20LA18880
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- e-plan: Convert existing detached 20'x20' garage to accessory dwelling with addition unit per ordinance LAMC 12.22 A.33(b)1
- Permit Issued
- Issued on 2/4/2021
- Issuing Office
- Current Status
- CofO Issued on 8/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2020 | LARRY LEE |
| Corrections Issued | 10/30/2020 | LARRY LEE |
| Applicant returned to address corrections | 12/22/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 12/23/2020 | MONICA RAMIREZ |
| Plan Check Approved | 1/27/2021 | MONICA RAMIREZ |
| Issued | 2/4/2021 | APPLICANT |
| CofO in Progress | 8/16/2021 | TROY SANDERS |
| Permit Finaled | 8/20/2021 | MICHAEL SMITH |
| CofO Issued | 8/20/2021 | MICHAEL SMITH |
| Permit Finaled | 8/20/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/23/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 11/23/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 1/4/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 1/5/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/22/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 2/22/2021 | Partial Approval | DAVID STEPANYAN |
| Sewer | 2/22/2021 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 2/22/2021 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 4/23/2021 | Corrections Issued | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2021 | Approved | DAVID STEPANYAN |
| Green Building Rough | 4/23/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 4/23/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 4/23/2021 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 5/12/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 5/12/2021 | Approved | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 5/26/2021 | Approved | SHAVONNE ESPINOZA |
| Insulation | 6/2/2021 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 6/8/2021 | Approved | ASHLEY THOMPSON |
| Shower Pan | 6/8/2021 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 6/14/2021 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 8/6/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 8/6/2021 | Corrections Issued | DAVID STEPANYAN |
| Final | 8/6/2021 | Corrections Issued | DAVID STEPANYAN |
| Gas Test | 8/6/2021 | Approved | DAVID STEPANYAN |
| Green Building Final | 8/6/2021 | Approved | DAVID STEPANYAN |
| Green Building Rough | 8/6/2021 | Approved | DAVID STEPANYAN |
| HVAC-Final | 8/6/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 8/6/2021 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 8/6/2021 | SGSOV Not Ready | DAVID STEPANYAN |
| Smoke Detectors | 8/6/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 8/16/2021 | Approved | TROY SANDERS |
| Final | 8/16/2021 | OK to Issue CofO | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/16/2021 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 8/16/2021 | Approved | TROY SANDERS |