2725 S BARRY AVE 90064

Certificate Information: 2725 S BARRY AVE 90064

Application / Permit
20016-10000-25959
Plan Check / Job No.
B20LA18874
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
e-plan check: Convert existing detached 2 car-garage to Accessory Dwelling Unit
Permit Issued
Issued on 9/10/2021
Issuing Office
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 ARSALAN SHABESTARI
Corrections Issued 10/30/2020 ARSALAN SHABESTARI
Quality Review Completed 11/21/2020 PRANITA SHAH
Applicant returned to address corrections 5/2/2021 ARSALAN SHABESTARI
Plan Check Approved 5/17/2021 ARSALAN SHABESTARI
Issued 9/10/2021 APPLICANT
CofO in Progress 5/2/2022 JOHNNY MIRANDA
Permit Finaled 5/4/2022 DANIEL ORRANTE
CofO Issued 5/4/2022 DANIEL ORRANTE
Permit Finaled 5/4/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/1/2020 DINAH GARIN
Sewer availability Cleared 12/1/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/2/2020 DINAH GARIN
Specific Plan Cleared 2/10/2021 PEDRO AYALA
Construction near power lines Cleared 4/12/2021 RIDWAN HARDY
Construction within easement Cleared 4/12/2021 RIDWAN HARDY

Contact Information

Contractor Williamson John Construction Inc; Lic. No.: 451421-B 8723 BLERIOT AVE      LOS ANGELES, CA 90045
Engineer Canby,, John Christopher; Lic. No.: NA21514       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 10/6/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Pre-Inspection 10/6/2021 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 10/14/2021 Approved JOHNNY MIRANDA
Green Building Rough 10/14/2021 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 10/14/2021 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 11/15/2021 Corrections Issued RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/16/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 11/16/2021 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/30/2021 Approved JOHNNY MIRANDA
Green Building Rough 11/30/2021 Approved JOHNNY MIRANDA
Insulation 11/30/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 11/30/2021 Partial Approval JOHNNY MIRANDA
Wood Frame 11/30/2021 Approved JOHNNY MIRANDA
Deputy Wood Construction 12/3/2021 Conditional Approval JOHNNY MIRANDA
Interior/Exterior Lathing 12/13/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 12/22/2021 SGSOV Approved JOHNNY MIRANDA
Final 4/25/2022 Corrections Issued JOHNNY MIRANDA
Final 4/27/2022 OK to Issue CofO JOHNNY MIRANDA
Green Building Final 4/27/2022 Approved JOHNNY MIRANDA
Smoke Detectors 4/27/2022 Approved JOHNNY MIRANDA