3828 1/2 S SUTRO AVE 90008

Certificate Information: 3828 1/2 S SUTRO AVE 90008

Application / Permit
20016-10000-25829
Plan Check / Job No.
B20LA18844
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert exisiting accessory building to detached ADU per state law GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 2/25/2021
Issuing Office
Current Status
CofO Issued on 6/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 HELEN NGUYEN
Corrections Issued 10/19/2020 HELEN NGUYEN
Quality Review Completed 11/18/2020 TU HUA
Applicant returned to address corrections 1/8/2021 HELEN NGUYEN
Applicant returned to address corrections 1/21/2021 HELEN NGUYEN
Plan Check Approved 2/18/2021 HELEN NGUYEN
Issued 2/25/2021 APPLICANT
CofO in Progress 6/24/2021 FREDDIE RIVERA
Permit Finaled 6/30/2021 DEROLD HAUFF
CofO Issued 6/30/2021 DEROLD HAUFF
Permit Finaled 6/30/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/26/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/26/2020 WALLIE JONG
Sewer availability Cleared 10/26/2020 WALLIE JONG
Construction within easement Cleared 12/21/2020 RIDWAN HARDY

Contact Information

Contractor Licg; Lic. No.: 1042051-B 756 S BROADWAY STE 409      LOS ANGELES, CA 90014
Engineer Lopez,, Mauricio Jose; Lic. No.: C36801 1391 N THIRD AVE      UPLAND, CA 91786

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/4/2021 Not Ready for Inspection ROBERT MCDOWELL
PLUMBING-Rough 3/4/2021 Not Ready for Inspection ROBERT MCDOWELL
Pre-Inspection 3/4/2021 Not Ready for Inspection ROBERT MCDOWELL
Sewer 3/4/2021 Not Ready for Inspection ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 3/24/2021 Corrections Issued DAVID FEILER
Gas Test 3/24/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 3/24/2021 Not Ready for Inspection DAVID FEILER
Pre-Inspection 3/24/2021 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 3/26/2021 Approved DAVID FEILER
Footing/Foundation/Slab 3/26/2021 Approved DAVID FEILER
Gas Test 3/26/2021 Partial Approval DAVID FEILER
Sewer 3/26/2021 Approved DAVID FEILER
Underground Mechanical 3/26/2021 Partial Approval DAVID FEILER
ELECTRICAL-Rough 4/16/2021 Not Ready for Inspection DAVID FEILER
HVAC-Rough 4/16/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 4/16/2021 Partial Approval DAVID FEILER
Underground Mechanical 4/16/2021 Approved DAVID FEILER
Deputy Drilled-In Anchors 4/21/2021 No Access for Inspection DAVID FEILER
Pre-Inspection 4/21/2021 Off-Hour Fees Due
BUILDING-Rough-Frame 4/23/2021 Approved SABAS ALONSO
ELECTRICAL-Rough 4/23/2021 Approved SABAS ALONSO
Green Building Rough 4/23/2021 Approved SABAS ALONSO
PLUMBING-Rough 4/23/2021 Approved SABAS ALONSO
Wood Frame 4/23/2021 Approved SABAS ALONSO
Insulation 4/26/2021 Not Ready for Inspection SABAS ALONSO
Deputy Wood Construction 4/30/2021 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/30/2021 Approved SABAS ALONSO
Insulation 4/30/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 4/30/2021 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 5/4/2021 Corrections Issued DAVID FEILER
Shower Pan 5/4/2021 Off-Hour Fees Due
Drywall Nailing 5/6/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 5/6/2021 Approved FREDDIE RIVERA
Shower Pan 5/6/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 5/7/2021 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 5/10/2021 SGSOV Not Ready FREDDIE RIVERA
Drywall Nailing 5/12/2021 Not Ready for Inspection DAVID FEILER
Shower Pan 5/12/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 5/27/2021 Not Ready for Inspection FREDDIE RIVERA
HVAC-Final 5/27/2021 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 5/27/2021 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Final 6/4/2021 Approved ROBERT MCDOWELL
Final 6/4/2021 Corrections Issued ROBERT MCDOWELL
Green Building Final 6/4/2021 Approved ROBERT MCDOWELL
HVAC-Final 6/4/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 6/4/2021 Approved ROBERT MCDOWELL
Pre-Inspection 6/4/2021 Approved ROBERT MCDOWELL
Service/Power Release 6/4/2021 Approved ROBERT MCDOWELL
Smoke Detectors 6/4/2021 Approved ROBERT MCDOWELL
Drywall Nailing 6/23/2021 Approved FREDDIE RIVERA
Final 6/23/2021 OK to Issue CofO FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/23/2021 SGSOV Approved FREDDIE RIVERA