10934 N MARKLEIN AVE 91345

Certificate Information: 10934 N MARKLEIN AVE 91345

Application / Permit
20016-10000-25784
Plan Check / Job No.
B20LA18809
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH NEW ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 9/7/2021
Issuing Office
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 ARSALAN SHABESTARI
Corrections Issued 10/30/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 2/9/2021 MONICA RAMIREZ
Applicant returned to address corrections 6/14/2021 MONICA RAMIREZ
Plan Check Approved 6/27/2021 KEVIN MORALES
Issued 9/7/2021 APPLICANT
CofO in Progress 12/26/2023 MATTHEW NELSON
Permit Finaled 4/16/2024 DANIEL ORRANTE
CofO Issued 4/16/2024 DANIEL ORRANTE
Permit Finaled 4/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/23/2021 GABRIEL ROBLES
Miscellaneous Cleared 2/23/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 2/23/2021 GABRIEL ROBLES
Sewer availability Cleared 4/12/2021 GABRIEL ROBLES
Construction near power lines Cleared 5/11/2021 RIDWAN HARDY
Construction within easement Cleared 5/11/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 6/7/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/27/2022 Conditional Approval MICHAEL SMITH
PLUMBING-Rough 7/5/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 7/8/2022 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 7/12/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 7/26/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 7/26/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/26/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 7/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
Pre-Inspection 7/27/2022 Partial Inspection JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 7/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
Service/Power Release 7/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
Deputy Wood Construction 7/29/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/1/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Partial Approval CHRISTOPHER DELLEFIELD
MERV13>=Rough 8/1/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 8/1/2022 Approved CHRISTOPHER DELLEFIELD
Sewer 9/27/2022 Approved JENNIFER RABUCHIN
Underground Mechanical 9/27/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 11/3/2022 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 11/3/2022 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 11/3/2022 Corrections Issued JENNIFER RABUCHIN
Shower Pan 11/3/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/23/2022 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 11/23/2022 Approved JENNIFER RABUCHIN
Green Building Rough 11/23/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 11/23/2022 Approved JENNIFER RABUCHIN
Insulation 11/23/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/23/2022 Partial Approval JENNIFER RABUCHIN
MERV13>=Rough 11/23/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 12/5/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/5/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/27/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/27/2023 Corrections Issued JENNIFER RABUCHIN
Final 2/27/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 2/27/2023 Approved JENNIFER RABUCHIN
Green Building Final 2/27/2023 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 2/27/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 2/27/2023 Approved JENNIFER RABUCHIN
Final 3/6/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/6/2023 Corrections Issued JENNIFER RABUCHIN
Final 6/28/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 6/28/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 6/28/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 6/28/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 7/31/2023 Not Ready for Inspection ROBERT GOLD
Final 7/31/2023 Not Ready for Inspection ROBERT GOLD
Green Building Final 7/31/2023 Not Ready for Inspection ROBERT GOLD
HVAC-Final 7/31/2023 Not Ready for Inspection ROBERT GOLD
PLUMBING-Final 7/31/2023 Not Ready for Inspection ROBERT GOLD
ELECTRICAL-Final 9/22/2023 Approved JENNIFER RABUCHIN
Final 9/22/2023 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 9/22/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 9/22/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/22/2023 Approved JENNIFER RABUCHIN
Final 10/2/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 10/2/2023 Not Ready for Inspection MICHEL ABAJAN
Final 12/13/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 12/13/2023 Approved JENNIFER RABUCHIN
Final 12/22/2023 OK to Issue CofO MATTHEW NELSON