1583 1/2 W 46TH ST 90062

Certificate Information: 1583 1/2 W 46TH ST 90062

Application / Permit
20016-10000-25747
Plan Check / Job No.
B20LA18792
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING TWO CAR GARAGE INTO AN ACCESSORY DWELING UNIT.
Permit Issued
Issued on 3/21/2022
Issuing Office
Current Status
CofO Issued on 2/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2020 APPLICANT
Assigned to Plan Check Engineer 10/20/2020 FARSHAD ALIMOHAMADI
Corrections Issued 11/23/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/30/2021 FERNANDO FLORES
Plan Check Approved 3/16/2022 FERNANDO FLORES
Issued 3/21/2022 APPLICANT
Building Plans Picked Up 3/30/2022 APPLICANT
CofO in Progress 2/21/2023 SABAS ALONSO
Permit Finaled 2/24/2023 DEROLD HAUFF
CofO Issued 2/24/2023 DEROLD HAUFF
Permit Finaled 2/24/2023 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 10/23/2020 JASON SHEETS
Address approval Cleared 3/23/2021 ROSA SILVA
Sewer availability Cleared 3/23/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 3/24/2021 ROSA SILVA
Construction near power lines Cleared 9/20/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/14/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 4/21/2022 Partial Approval SABAS ALONSO
Underground Mechanical 4/21/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 4/28/2022 Approved SABAS ALONSO
PLUMBING-Rough 5/18/2022 Approved SABAS ALONSO
Insulation 7/19/2022 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 7/19/2022 Not Ready for Inspection SABAS ALONSO
Insulation 7/26/2022 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 7/26/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 7/29/2022 Approved SABAS ALONSO
HVAC-Rough 7/29/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 8/3/2022 Approved SABAS ALONSO
Green Building Rough 8/3/2022 Approved SABAS ALONSO
Insulation 8/3/2022 Approved SABAS ALONSO
Drywall Nailing 8/17/2022 Approved SABAS ALONSO
Shower Pan 10/13/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/25/2022 Approved SABAS ALONSO
ELECTRICAL-Final 12/20/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 12/20/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 12/20/2022 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 12/20/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 1/5/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 1/5/2023 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 1/5/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 1/5/2023 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 1/5/2023 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 1/23/2023 Approved SABAS ALONSO
Final 2/7/2023 No Access for Inspection SABAS ALONSO
ELECTRICAL-Final 2/16/2023 Approved SABAS ALONSO
Final 2/16/2023 OK to Issue CofO SABAS ALONSO